The Uncle Gnarley Blog has a new website. Click here to visit www.unclegnarley.ca to view the latest posts!

Monday 24 January 2022

THE LABRADOR ISLAND LINK IS “SUNK COST”

We should be worried that GNL will double down as big problems persist and costs continue to rise on Soldier’s Pond and the LIL, all the way to Muskrat Falls. It seems destined to be a victim of the "sunk cost" fallacy which describes a tendency to sink more money into a scheme in which a large investment of time and money has already been made, regardless of whether the costs outweigh any benefits.

Last week’s post described the chief conclusion of the second Haldar and Associates report that the Labrador Island Link transmission line (LIL) is under-designed and may need salvaging as often as every six years.

The Report was ultimately conducted for Public Utilities Board which wanted more data to help forestall a repeat of the 2014 outage known as #DarkNL.

#DARKNL WAS BAD. A NEW REPORT ON LILWILL LEAVE YOU COLDER refers to an LIL failure in January 2021 when rime ice damaged a number of towers in southern Labrador, which took seven weeks to repair.  

The Haldar report concluded that the “return standard” of the LIL (the on-average period during which a transmission line will withstand weather conditions based on its design) was far lower than that claimed by Nalcor. The consultant found that it could be as low as 1:6 years and estimated the repair period, under ideal conditions, to be three to six weeks.

When Manitoba Hydro International (MHI) reported to the PUB in 2012, the firm recommended a return period of 1:150 years using an alternate supply (i.e. the Holyrood Plant). They proposed a return standard of 1:500 years without an alternate supply...and "an even higher standard in the alpine areas."

Like the project budget and most things Muskrat, the return standard was cooked up. Nalcor needed to close Holyrood; the forecast fuel savings represented the ostensible basis of Muskrat Falls’ economic viability.

Hardar notes that “Hydro has developed, and is continuing to develop, detailed engineering solutions…to expedite re-energization of the LIL following a bipole (two lines) failure.” Wood poles and modular aluminum structures, in addition to better logistics for faster access to a damaged section of the line, are being examined. 



These initiatives might sound encouraging if at issue were old towers scheduled for refit. Instead, under the microscope is a brand new, barely used Labrador Island Link, an 1100 km. transmission line that has never been energized to more than half of its design capacity. 

The very same people who defended its original substandard design are now permitted to play with more public money to cover up their monumental error (deception and recklessness, actually).  This is infuriating enough, but the implications of the problem are maddening.

Naturally, most people will see the issue in the context of their own power security. Those who recently purchased generators expect to be protected for the duration of an LIL failure. But an under-designed LIL poses other problems for the province that compound the existential challenge of paying for this nearly $15 billion project. 

Any “fix” of the 3,224 towers erected, whether experimental or a response to catastrophic damages, is sure to add tens of millions of dollars of Operation and Management (O&M) costs annually, and additional hundreds of millions to remediate the TL every half dozen years or so, as weather tests Nalcor’s technical temerity. 

Haldar does not address climate change and how related extreme weather events are already giving fright over infrastructure robustness in many towns and cities, including within Canada. Eventually, NL Hydro will be forced to add these events to the calculation of the “real” return standard of the LIL. 

The current O&M budget is still untested, too, the estimate having doubled after Stan Marshall became CEO and dialed back when the requirements for rate mitigation became unachievable. That won’t make the actual costs any lower. 

Of course, lawyers will constantly remind GNL, as they have done already, to think of commitments made to Nova Scotia in relation to the Maritime Link. But as fellow blogger, PlanetNL notes, “there ought to rationally be a tipping point” in this LIL salvage operation, one “where suffering a settlement agreement with Emera to abandon the Maritime Link is preferable to dumping more money into the ML or the LIL.” 

The Haldar report logically leads us to another conclusion that Holyrood – or an equivalent replacement plant - will have to be kept running as the permanent backup to both TLs. That means the public should be on-guard that Holyrood becomes the backup supply for Nova Scotia’s Emera, too. 

Except that PlanetNL knows provincial politicians will spend an empty Treasury dry before they will ever arrive at a conclusion as sensible as abandoning the LIL. 

David Vardy and PlanetNL have written extensively about the Muskrat Falls project’s lack of viability and the shortcomings of the “rate mitigation” scheme concocted by the Furey Administration, with the Federal Government’s assistance. At all times, GNL has assumed that Muskrat is, at least, technically viable project and is worth spending large annual subsidies will make the financial problems go away. On this level, too, Vardy and PlanetNL argue that the thesis is wrong. 

The Haldar Report confirms, however, that the LIL’s low return standard makes it technically untrustworthy, too. Haldar only reviewed the LIL. Other major issues prevail: Three patched up synchronous condensers at Soldier’s Pond, vital to the operation of the electrical grid, are fitted with elliptical bearings which lower vibrations levels in the foundation. Nalcor doubts it is a long term “fix”. 

Software issues keep the project at half production. As yet unproven China-purchased generators (Nalcor neglected to have their manufacture surveyed, though the large Units were the first of their size produced by the manufacturer) sit in the powerhouse. Add the North Spur stability problem and a Water Management Agreement, which the Quebec Superior Court was limited in its ability to resolve. All compound the technical weaknesses of the project. 


Governments are not capable of big, courageous decisions; most of them made are of the incremental kind. For that reason, the financial bleed of rate mitigation promises to be compounded by a series of multi-million dollar “band-aids”, none of which will can cure the diabolical array of problems that, at its birth, entered Muskrat’s DNA.  

Holyrood will have to be kept running as the backup to the LIL, adding to the annual rate mitigation requirements. Does Premier Furey have the cohunes to tell Emera and the Nova Scotia UARB of their failure to perform an adequate assessment of the LIL, and that they should pay for their own bad decisions? 

Someone will need to consider all those issues, not separately as they present, but together – now - before their collective financial consequences start to make the current price tag look cheap. 

Face it: There is already ample evidence that the LIL won't be anything better than a rotten lemon.  The other assets are not giving off great smells either. 

The correct incremental decision, therefore, is to shut the LIL down now, and let the MF powerhouse operate until it doesn’t. That is the only answer to the PUB’s worry over the question of power security on the Island. 

A cryptocurrency mining industry in Labrador will bring in some revenues until the decision to close Muskrat Falls is made. 

A perfect idea for a province too quick to fall in love with a good story!