Guest Post by PlanetNL
PlanetNL.4 - Mothball Muskrat Now
Previous PlanetNL instalments have detailed how the uneconomic
Muskrat project threatens to destroy NL Hydro and ratepayers or, if the subsidy
route is chosen, Government and taxpayers. The painful third alternative
is to choose to stop the project and have the Premier call on Ottawa to act
fully and promptly on the murky Federal Loan Guarantees of $7.9B.
Even with the federally guaranteed debt removed, serious
issues remain. Ratepayers still face large rate increases and the
Provincial Government must record a total loss of equity. Emera would
suffer contractual losses and demand compensation. Ottawa would be
divided on whether to act as many other provinces will not support the
bailout. A substantial and raucous debate is sure to erupt whenever
Ottawa publicly considers this request.
…………………….
…………………….
How Weak is the Muskrat Business Case?
The decision to stop the project is simple. Due to inevitable rate increases already set into motion before Muskrat completion, electricity demand on the island of Newfoundland is sure to fall to levels that make Muskrat power completely unnecessary within the province (along with the Holyrood thermal plant Muskrat was intended to replace). There is no longer an in-province energy justification for the project – it will be completely surplus to local needs. Nalcor and Government simply never factored in demand elasticity or accurate demographics and remain in denial of these fundamental laws of economics.
Export of power outside NL provides the only true and direct
revenue opportunity from Muskrat. Nalcor forecasts export revenue of
about $50M annually as shown in their October 3, 2017 RFI response reviewed
in detail in PlanetNL3. As developed in that last post, Government will
find itself having to inject a $500M subsidy into Hydro to enable Nalcor to
earn the $50M revenue on power exports. That’s an exceptionally bad
business model that threatens to be repeated for 50 consecutive years.
Digging deeper into that RFI response, issues of subsidy
aside, Nalcor’s forecast of Operations and Maintenance (O&M) costs alone are found to
begin at over $120M in 2021 and grows steadily from there. Here lies the
other core flaw of the business case – one that always proves fatal.
Private sector businesses that can’t cover their O&M costs
and see little or no chance of market turnaround will quickly decide to stop
operations rather than continue to lose money. They will either scrap
their assets for salvage or just walk away. Whether the project is
paid-off or still in construction is immaterial. Equity is written off
and remaining debt becomes a pure liability without asset-backing, poisoning
the balance sheet.
Everything that can’t be sold or moved for use elsewhere is a
sunk cost.
The Newfoundland and Labrador landscape is littered with
defunct mines, paper mills, and fish processors that have made exactly those
decisions when boom times go bust. Canada as a whole has a long history
of the same. The Provincial and Federal Governments have participated in
many business busts in the past and the decision to stop Muskrat should be as
obvious as any example before it.
Mothballing the Project: A Brief Scope and Budget
The massive structures at the Muskrat Falls generation site
will be too costly to demolish.
Neither ratepayers nor taxpayers could afford the probable
billions for a removal project. In the short-term, the structures and
site must be tidied up, powered, lit, heated in places and steadily maintained
to prevent them from decaying into public safety and environmental
hazards. A large fence must be built around the site, the grounds kept
up, and 24-hour security provided – our province’s very own Chernobyl-lite.
Consultants would perform routine inspections to certify
structural stability and recommend any modifications and maintenance. A
guesstimate annual budget to maintain the site is $30M, likely to be covered by
NL Hydro ratepayers. Longer-term, this cost threatens to grow as the site
ages therefore a remediation project to permanently stabilize the structures
and reduce public safety hazards would be sought at a probable cost of up to
$0.5B if it can substantially eliminate the annual costs.
There are significant hazards posed by 1450kms of
transmission lines that if not maintained will eventually collapse or be the
target of vandalism and metal-scavengers. Removal of the wires and
towers will be a practical and urgent necessity. There may also be
reasons to take up the Strait of Belle Isle subsea cable, remove the terminal
stations at the Straits Crossing and downsize or eliminate the Soldier’s Pond
substation. A budget of $1.0B is a reasonable first guesstimate.
If the project continues to advance and an eventual
mothball decision made later, more new capital will be required, entirely on
the Province’s tab. Continuation of construction also includes
substantial risk of new overruns. Continuation also ensures more
equipment is installed at the facility, resulting in increased remediation
scope and reduction in the salvage value of materials that could have been
diverted before delivery. These additional costs in the billions cannot
be justifiably incurred to complete a project that will bleed money in
perpetuity. The time to stop now.
Federal Loan Guarantees and Political Issues
Without a federal bailout of the $7.9B loan guarantees, the
self-destruction of the Province is destined to end up a costlier national
problem. Ottawa must ultimately decide whether calling in the
Muskrat loan guarantee is a necessary preventative measure against more serious
financial peril.
Most of the country would grieve a decision by Ottawa to bail
out the Newfoundland project. Quebec had definite misgivings of a
competing project being de-risked by Ottawa when they received no such direct
benefit on their latest hydro projects. Ontario, which earlier this year
executed a $20B+ electricity rate reduction financing scheme of its own, might
demand its share of relief from Ottawa. Then there are dubious ongoing
hydro projects in British Columbia and Manitoba where their Governments may
seize an opportunity for Federal backing on abandonment of their projects with
less harm to their ratepayers and taxpayers.
Nova Scotia and Emera will be faced with significant direct
losses. Ottawa will have to pick up the Federal Loan Guarantee of $1.3B
made to Emera on the Maritime Link project: they will scornfully look east to
Newfoundland for compensation on their balance of lost capital costs.
Besides that, Nova Scotia’s plan to close their coal burning thermal generation
plants will be delayed by years and they must go back to the drawing board for
another solution.
The Province must be wary that Ottawa and other provinces may
be seeking to extract other pounds of flesh. Threats may arise to
expropriate offshore oil equity holdings and royalties, the recall block of
Upper Churchill, possibly the Province’s entire Upper Churchill holdings, and
possibly NL Hydro itself. None of these should make sense to Ottawa as
the worsening of the already precarious Newfoundland economy would accelerate
the Province toward insolvency and an even more costly general economic bailout
would follow.
Comparison to Other Provinces with Failing Hydro ProjectsAs mentioned above, other provinces are simultaneously building major hydro projects that, like Muskrat, have a high probability of being completely redundant for in-province energy demand and loss-leaders for export revenues. However, they differ hugely when measured by their risk to ratepayers and society.
The British Columbia Site C project if fully built to no
useful purpose might raise BC rates by about 1c/kwh, keeping their rates close
to the average Canadian price. Manitoba might not incur much higher an
increase if its projects fail yet they would still have below average price
electricity. Hydro Quebec could swallow their pride on their latest
projects, raise their rates by only a fraction of a cent and still have the lowest
rates in the country. The ratepayers and taxpayers of those provinces
won’t be nearly as seriously affected by their price of failure as in
Newfoundland.
Newfoundland’s comparatively small size cannot absorb the blow
of a publicly funded megaproject disaster. Even after the Federal Loan
Guarantees are called upon, the Province’s responsibility for lost equity,
interest expenses, and mothballing expenses will take a heavy toll.
Electricity rates are virtually certain to become the highest in the country
causing considerable personal hardship for many. NL taxpayers will
further bear the burden of at least $4B of additional net public debt, widening
annual deficits and decreasing quality of essential government services.
The Newfoundland and Labrador Government must show wise
leadership in demonstrating to Ottawa and other provinces that these high-risk
projects are not all equal and that the peril and folly of Muskrat is entirely
unique in its severe and long-lasting socio-economic impact. The Muskrat
bailout is imperative and does not imply that any other province should receive
the same consideration.
Action Required
The Premier is directly responsible for communicating to the
Prime Minister the urgency and peril of the situation and there is no evidence
that he has yet done so. This inaction makes him directly responsible for
the ongoing potential billions in additional losses that will accrue solely to
the Province’s debt. The Premier must appeal to the Prime Minister to
make this matter an urgent priority, so the project can be stopped at the
soonest possible date.
While the Premier’s public message has consistently been to
finish the project, we can hope he is rational enough to consider the
cancellation alternative proposed here. According to data found in a
just-released Oversight Committee quarterly report, there is $2.5B left unspent
as of the end of September. A substantial part of this could presumably
be saved to fund the post-cancellation requirements. Completion
will exhaust those funds and needlessly waste billions more.
Next Post
Several alternative operational scenarios will be presented to
demonstrate why full abandonment is the best option; the Provincial issue of
power backup is reviewed, not additional power supply plus some closing
comments on the tangle with Emera and Nova Scotia.
Sources
and Recommend Reading
Nalcor RFI responses: https://nalcorenergy.com/about/transparency-accountability/atippa/responses/
-
Select PB-651 for the Oct.3, 2017 response with
detailed PPA costs 2021-2070
-
Select PB-555 for the Aug.31, 2017 response with
detailed Dividend projections 2021-2070
Muskrat Falls Project Oversight Committee – Quarterly ReportEnding Sept.30, 2017 – publicly posted (est.) Nov.3, 2017:
Annual Reports of Emera, Hydro Quebec, Ontario Hydro,
Manitoba Hydro and BC Hydro were reviewed to assess rate impacts
and trends (hyperlinks not included)
The BCUC report on evaluation of Site C, released November
1, 2017 can be found here. Numerous submissions to the Inquiry were also
examined (hyperlinks not included)
Brand Command, Alex Marland (2016) – Anyone from the
Province pitching the Muskrat problem to Ottawa should be sure to have read
this book: Brand Politics: Canadian Politics and Democracy in the age of Message Control by Alex Marland.
About
PlanetNL
Frustrated by the continuing lack of honest and credible
information from Nalcor and Government, PlanetNL, having a suitable analytical
background, is presenting independent research and calculations. This is a spare time activity outside of
regular professional commitments. All
key information used to develop the views and analysis are publicly available. The analysis cannot avoid entering public
policy space: if Government or Nalcor wish to refute the analysis, they are
welcome to present an open and honest rebuttal.