A year ago I started an article
in reaction to Danny William’s speech to the Board of Trade but never completed
it.
Now that Nalcor’s management of
Muskrat Falls will be scrutinized. It is timely to examine some issues for the
investigation.
1.
The mandate of NL Hydro / Nalcor is to provide
power to the citizens of the Province at the lowest possible cost. Early in my
career I worked in the Systems Planning Group of Shawinigan Engineering under
the direction of George Scruton who was an engineer of impeccable integrity.
Most of our work involved system expansion studies. George insisted as a
fundamental principle that the cost of
all the options – capital, fuel, operation and maintenance and related financial
costs be developed to similar standards of accuracy and that competing options
be equivalent in terms of reliability. In the case of Muskrat Falls I
believe that the probability of bias was high given the big disparity between the
efforts and resources devoted to the comparisons between the Isolated Island
Option and Muskrat Falls: perhaps $ 3 million, for the Isolated Island Option
versus $420 million for Muskrat Falls. Additionally the documents I have seen show
little evidence that optimization of the Isolated Island System was ever seriously
attempted. The lowest cost power would certainly have been obtained by
completing Phase 3 of the Bay des Espoir Development (75 MW) that could have
produced power at a low enough cost to allow a reduction in power rates!! Terra Nova Development with a capacity of 144
MW would also be interesting; as well as the addition of a third unit at Cat
Arm which already incorporates provisions for a one unit expansion. But none of
these projects were ever considered, as far as I can tell. I was never
convinced that Muskrat Falls was truly the lowest cost alternative.
2. Danny Williams argued that cost over-runs were usual with large mega projects and were to be expected. As an engineer I challenge this assumption. It is interesting to compare related experience: notably Churchill Falls Development, one of the largest private sector developments at the time, which was completed ahead of schedule and under budget. More recently, experience on the James Bay Complex in Quebec was positive: Phase 1 of the Complex was completed 4% under budget while the individual projects of Phase 2 range from “on budget” to 3.2% under budget for the five projects in Phase 2. What can explain the difference between these projects and Muskrat Falls? I think that there are a couple of reasons that could (at least in part) explain the different experiences:
a. The
impact of three mega projects under construction at the same time, with Muskrat
Falls the being last of the three, following Vale Smelter and Hebron, does not
seem to have been addressed by Nalcor in their presentation to the Reference to
the PUB in 2012. Neither Nalcor, PUB
officials or any of the intervenors seem to have noticed this elephant in the
room. However, contractors were well aware of the problem. I believe the
cost impact of failing to account for this situation could have added 25% - 30%
to the Project cost.
_________________________________________________
Also by Phil Helwig:
How Reliable Will Muskrat Power Be?
__________________________________________________
_________________________________________________
Also by Phil Helwig:
How Reliable Will Muskrat Power Be?
__________________________________________________
b. I
believe that Hydro Quebec’s estimating procedures, following guidelines of the
Quebec Association of Consulting Engineers, were much more rigorous than
applied by Nalcor. These procedures involved preparation of a Detailed Project
Definition (Avant-project détaillé) report typically, described as a “bankable”
report. Also on very large projects a Control Estimate was usually prepared. This was my impression from working on two
Hydro Quebec projects with a major Quebec engineering firm in Montreal. I
also think that Hydro Quebec cost estimators are very experienced and
competent. However, these two points cannot explain the magnitudes of the cost
over-run at Muskrat Falls. Is Nalcor’s limited experience in the project
management of mega projects to blame? See below:
3.
The first issue concerns Nalcor’s experience in
project management of very large projects, which is nil. Originally, the
project management phase was included in SNC-Lavalin’s scope of work. I
understand that Nalcor felt it could realise significant savings by taking over
this facet of the work themselves. I do not know whether SNC-Lavalin had any
further involvement in project management. Nalcor appears to have assumed
responsibility for this role and their performance or deficiencies need to be
assessed. Remarks from a senior SNC-Lavalin engineer concern two Nalcor
practices that were judged to be unproductive as below:
a.
The practice of appointing individuals from NL
Hydro or sub-consultants to track / oversee certain components of design or
planning was often counterproductive as these individuals often did not have
the necessary experience or training to contribute to design preparation and whose
contributions were limited and sometimes negative. Did this decision also
compromise efficiency?
b.
My confidant also feared that Nalcor would not
be tough enough in evaluating claims for “extras”.
c.
Did the decision to carry out most of the design
work in St. John’s deprive the project of the most experienced and capable of
SNC-Lavalin’s staff?
d.
It is noted that Nalcor use AACE Guidelines for
preparation of their capita cost estimates. These guidelines note that simply
following Guideline procedures will not guarantee a quality estimate but that
the quality of the estimate ultimately depends on the accuracy of the inputs.
The following lists elaborate:
I argue that Nalcor did not
assess market conditions appropriately. Were they equally, inattentive in
considering the rest of these criteria?
I ask that the enquiry
investigate the points I have raised above.
Phil
Helwig, P.Eng
Hydro-engineer
_________________________________________________________
Editor's Note:
Phil Helwig has had a varied engineering career in both
education (8 years) and in design and technical management (44 years). Most of
his formative experience was with a small company in Newfoundland (ShawMont)
which valued versatility, as a result Phil was able to develop expertize that
goes well beyond the skills set normally associated with his formal area of
competence, as a hydrotechnical specialist. His main area of expertise is in
the fields of hydropower and water resources where he has been involved in
investigations, economic planning and project optimization studies and detailed
design. He has been responsible for several innovations in Canadian practice:
notably, the design of Cat Arm Hydel unlined pressure tunnel (head = 386 m) and
“bathtub overflow spillway” and design of Hinds Lake Power Canal based on
natural armouring (the first application of this technology in hydro design
worldwide) and the design of Paradise River double curvature arch dam only the
third arch dam ever built in Canada. More recently from his experience in South
Asia he has developed expertize in design of hydraulic structures to handle
water borne sediment. His latest interest is in the field of eco-hydraulics. In
2004 Phil formed his own company, Helwig Hydrotechnique Ltd. and has worked on
four continents in three languages.
Technology transfer is an integral part of all Phil Helwig’s assignments.