There is
little doubt the A-G is deeply concerned over the state of the Province’s
finances. In his 2014 Report to the House of Assembly, gravitas is expressed over our dependency on petroleum
revenues, the structural deficit, the growing debt, a declining GDP, and other issues.
Premier Davis would have us believe recent Administrations have exhibited sound fiscal stewardship and there is no need for change. The truth is the Williams’ years, and since, have been marked by a level of financial recklessness that is not only repugnant; it will take years to repair.
Premier Davis would have us believe recent Administrations have exhibited sound fiscal stewardship and there is no need for change. The truth is the Williams’ years, and since, have been marked by a level of financial recklessness that is not only repugnant; it will take years to repair.
The purpose
of this Blog is to not just chastise unwise and undisciplined politicians. It seeks to illuminate serious public
policy issues. The A-G's Report needs plenty of light.
The statements that follow are extracts from the 2014 Auditor General’s Report, specifically Chapter I entitled “Comments of the Auditor General” and Chapter 5, “The Financial Condition of the Province”. I think those selections represent his most prescient “observations”. (Click on this Link and go to Chapter 5 for more details.)
In my concluding comments I beg, yes, beg the Auditor General to display the utmost courage and uncloak Nalcor CEO Ed Martin and the Muskrat Falls project. First, the Auditor General has the floor:
Public Spending
·
Since 2005, the
Province’s expenses have grown from $5.0 billion to $7.9 billion in 2014, an increase
of $2.9 billion, or 58.0%.
·
Per capita
expenses in Newfoundland and Labrador are approximately 45% higher than the
average of all other provinces and are the highest of all the provinces in
Canada.
Demography and Population
·
The population of
Newfoundland and Labrador is getting older.
·
In 1971, the
percentage of the population that was 60 years of age or older was 9%, while in
2013, 25% of the population is 60 years of age or older. Meanwhile, the
percentage of the population that is under 15 years of age has declined from
37% in 1971 to 14% in 2013. Furthermore, in 2026 it is forecasted that 33% of
the population will be 60 years of age or older, while 15% of the population
will be under 15 years of age.
Muskrat Falls
Muskrat Falls
·
The size and
complexity of the development creates considerable risk that the Province and
the proponents will have to carefully manage during the construction phase.
GDP Growth
GDP Growth
·
Real GDP is
virtually unchanged from $29.7 billion in 2007 to a forecast amount of
$29.9 billion in 2014. Real GDP is
forecast to decline from 2014 to 2016.
·
The current
softness in commodity prices has the potential to significantly impact the
forecast deficit in 2014-15 and
the Province’s plan to return to surplus by 2015-16.
Surplus
·
The cumulative
value of surpluses recorded by the Province from 2004-05 to 2013-14 of
$4.6 billion was almost entirely
the result of payments received under the Atlantic
Accord arrangements.
Deficits and Debt
· The
forecast deficit of $538 million in 2014-15, will be the third deficit in a
row.
· Net
Debt of the Province at March 31, 2014 was $9.1 billion.
· By
March 31, 2016, Net Debt will likely exceed $10 billion.
• In
2013-14, oil royalties were $2.1 billion, or 28.4% of total revenues. In 2011-12,
oil royalties peaked at almost $2.8 billion.
oil royalties peaked at almost $2.8 billion.
• The
impact of the offshore sector on the overall revenues of the Province is even
greater
considering that a significant portion of corporate income tax, personal income tax, and
other direct, indirect or induced revenues result directly from activity in the offshore sector
as well.
considering that a significant portion of corporate income tax, personal income tax, and
other direct, indirect or induced revenues result directly from activity in the offshore sector
as well.
Oil Production
·
Annual
production of offshore oil has shown a downward trend since 2007.
The Public Sector Pension Plan
· Beneficiaries under the Public Service Pension Plans have increased by 17,000, or 33%,
since 2004.
· Since 2007-08, the unfunded liability has increased by 117%, and as a result, at March 31, 2014 the total unfunded liability is now greater than it was at March 31, 2005, despite in excess of $3.6 billion in special payments over that period.
* ...employee future benefits expense has increased from $233 million in 2007-08 to $890 million in 2013-14 - an increase of $657 million or 282%.
· Recent negotiated changes to the Public Service Pension Plan may impact the annual expense, however, the magnitude is uncertain at this time.
What do we
make of these observations?
First, I
suggest they need to be weighed in the context of the comments contained in
Part I of this two part series. The A-G is less crusader than he is economic historian. The Province needs a champion providing oversight of its fundamental economic and financial interests.
Second, on the Muskrat Falls project, the A-G warns that Nalcor "will have to carefully manage during the construction phase". With respect, that is empty rhetoric.
Skilful oversight is the only way the worst impacts of the largest publicly funded construction project in the Province's history can be contained. The A-G must know that the project is on a cost path that will dramatically increase the public debt and impair the Government's budgetary obligations. The A-G needs to expose Nalcor's excesses, examine the contracts already let, and analyse the extent to which they expose the public purse to unfettered risk. He also needs to slam the Government for its "sham" oversight Committee.
Skilful oversight is the only way the worst impacts of the largest publicly funded construction project in the Province's history can be contained. The A-G must know that the project is on a cost path that will dramatically increase the public debt and impair the Government's budgetary obligations. The A-G needs to expose Nalcor's excesses, examine the contracts already let, and analyse the extent to which they expose the public purse to unfettered risk. He also needs to slam the Government for its "sham" oversight Committee.
______________________________________________
Related Reading:
A-G's REPORT IMPORTANT BUT NOT COMPLETE (PART I)
______________________________________________
While the media continues its preoccupation with traffic tie-ups and weather, we rely on a few institutions like the Office of the A-G, ordained by Statute, to stay above what Thomas Hardy calls the “madding crowd”.
A-G's REPORT IMPORTANT BUT NOT COMPLETE (PART I)
______________________________________________
While the media continues its preoccupation with traffic tie-ups and weather, we rely on a few institutions like the Office of the A-G, ordained by Statute, to stay above what Thomas Hardy calls the “madding crowd”.
If the A-G wishes
to avoid history’s condemnation, he will express more than the equivalent of a "tut, tut" over the Government's unbridled excess; he will stiffen his spine and head over to
examine Nalcor’s books. He will
unabashedly exhibit the moral courage that should always be a hallmark of his
Office.
The A-G's reluctance may be connected with the right given the Nalcor CEO to restrict publication of information he deems "commercially sensitive". That is not a reason to be fearful or to hide. On the contrary, any dark corner where the expenditure of huge dollops of public money is conducted, in secret, is where we should find him.
If Ed Martin wishes to restrict information the A-G deems appropriate for public viewing, let him. The A-G has the right and obligation to report the same to the House of Assembly and to the public thereby.
Muskrat is a project once "sold" as a $6.2 billion investment. At last update, the figure has reached $8.3 billion including interest during construction. Nalcor's monthly reports fail to note schedule slippage and continuing cost overruns. Some highly placed engineers suggest Muskrat is a project heading towards a final cost of $13 billion; others place the figure at 2.5 times the estimate at DG-2. The implications of such an outcome are staggering. The obligation of the A-G to spring into action is incontestable.
The A-G's reluctance may be connected with the right given the Nalcor CEO to restrict publication of information he deems "commercially sensitive". That is not a reason to be fearful or to hide. On the contrary, any dark corner where the expenditure of huge dollops of public money is conducted, in secret, is where we should find him.
If Ed Martin wishes to restrict information the A-G deems appropriate for public viewing, let him. The A-G has the right and obligation to report the same to the House of Assembly and to the public thereby.
Muskrat is a project once "sold" as a $6.2 billion investment. At last update, the figure has reached $8.3 billion including interest during construction. Nalcor's monthly reports fail to note schedule slippage and continuing cost overruns. Some highly placed engineers suggest Muskrat is a project heading towards a final cost of $13 billion; others place the figure at 2.5 times the estimate at DG-2. The implications of such an outcome are staggering. The obligation of the A-G to spring into action is incontestable.
I beg you to show some courage, Sir.