Monday, 25 March 2019

MORE PRE-SANCTION FRAUD OR INCOMPETENCE?

Guest Post by PlanetNL
PlanetNL23: Backup Power Risks Reveal More Pre-Sanction Shenanigans

Two new reports on the Public Utilities Board (PUB) website shatter the illusion that the Muskrat Falls project will avoid the need for oil-fired generation in the province.  Upon decommissioning of the 490MW steam generation capacity at the Holyrood Thermal Generating Station, there is a critical reliability scenario arising in the all too likely event the Labrador Island Link (LIL) experiences an outage that will lead to a 500MW capacity deficit on the Avalon Peninsula.  Another report identifies that even when Muskrat runs optimally, there is insufficient capacity reserve without the addition of two new 58.5MW Combustion Turbines (CTs).

This new information gives further evidence of how Nalcor distorted the comparison of the Isolated vs Interconnected pre-sanction scenarios to favour Muskrat.  As reality sets in, Nalcor finds itself left with only one viable solution: the installation of several new diesel CTs, likely on the very same Holyrood site.  The irony of building the colossal Muskrat Falls megaproject for the purpose of closing Holyrood, only to find that a direct replacement must be constructed, is an astonishingly shameful exposure of Nalcor’s deceit.