Guest Post by PlanetNL
PlanetNL2 – Muskrat Will Cause Monumental Government Debt and Social Pressure
PlanetNL2 – Muskrat Will Cause Monumental Government Debt and Social Pressure
In last
week’s inaugural PlanetNL, the post-Muskrat rate hike was predicted to rise quickly
into the 30-35 c/kWh range and then to continue to spiral upward as the market
continually fails to deliver required revenue.
This pricing model should be considered theoretical because it’s too
insane to think the Government would actually allow rate runaway to happen and
not attempt to intervene with a better alternative that can preserve stability
of the market and the survival of the utilities that serve it.
Logically,
Government must limit rates to some sustainable level that ratepayers can
bear. They must also not allow the bankruptcy
of NL Hydro and the Nalcor companies as this would lead to the evisceration of
core Government assets to outside interests.
Government has
little choice but to lean heavily on the public purse of the taxpayer to make
up the shortfall in utility revenue.
Government
has the exclusive authority to decide what rate the market might reasonably bear
and then accept that the difference must be provided by an operating subsidy. Two months ago, Premier Ball indicated in an
article published by The Telegram that his Government is aiming for a domestic
rate of 17 c/kWh and he acknowledges a $400M deficit that Government will have
to pay. A link to the article is
provided below in the References section.
The 17 c/kWh
level is still 70% higher than rates of recent years and sure to cause
substantial energy sales contraction as consumers of all types adapt by
reducing consumption and fleeing to non-electric or highly efficient electric heating
options. As explained in PlanetNL1, NL
Hydro production and sales would likely plunge from 7000GWh to 5000GWh thereby
eliminating any domestic demand for Muskrat Falls power.
Allowing
that industrial customers will get negligible increases on their already deeply
discounted rates, the total island system utility revenue will rise from $700 M
to about $800M.
This
increase of merely $100M will come into effect with the proposed 13% Hydro rate
increases in 2018 and 2019. Revenue
growth from rate increases will be effectively exhausted before Muskrat
start-up in 2020. Muskrat payback shall
evidently be allocated 100% to Government.
Measuring the Revenue Chasm
The required
utility revenue inclusive of Muskrat payback was shown in PlanetNL1 to be at
least $1350 and possibly up to $1550M even with Holyrood fuel savings factored
in. Choosing a value in the middle at
$1450M and then subtracting the maximum realistic ratepayer revenue amount of $800M
leaves an annual shortfall of $650M.
To reduce
this deficit, the NL Hydro and Nalcor electricity lines of business will be
asked to look inside their operations for opportunities to reduce costs or
raise revenues in their other markets. Labour
costs will be the biggest target with possible tactics including a salary
freeze, wage rollbacks and some layoffs or attrition through retirements. As over 90% of Hydro revenue occurs in the
Newfoundland island market, little will be gained by attempting to raise rates
elsewhere.
In total, Hydro
and Nalcor could scrape together at most a few tens of millions in operational
savings and revenue adjustments leaving Government to face a minimum subsidy in
2021 of $600M. How then does Premier
Ball have it measured at $400M?
Giving Up Dividends
Nalcor has a
formal 50-year Muskrat operations cash flow forecast of all dividend income anticipated
to be delivered to Government as return on equity: this document, updated by
Nalcor since the June 23, 2017 Muskrat project update, was recently obtained
through a Request For Information (ATIPP) - a link is provided below.
Before
assessing the expected dividends, recall that the Muskrat project was initially
promoted to the public as a project ratepayers would affordably pay the entire
cost of through reasonable and fair rates while the export cash flows were
supposed to be the gravy that would make Government rich.
In the first
instance, ratepayers will not find 17 c/kWh affordable and fair. It will be the highest electricity rate in
the country. In the second instance, in the
first year in which payback is required, 2021, the total dividend estimate of
$185M is not especially rich. It’s barely
1.5% on total capital and just 4.6% on the Government’s $4.0B in equity. These are unimpressive returns.
What’s worse
is that Premier Ball seems to be indicating that his Government will decline to
accept the dividends – this appears to be how he limits the required subsidy to
$400M. Reading deeper between the lines,
if no earnings are returned from the project, there will never be payback on equity:
Premier Ball is tacitly acknowledging that Government’s
$4.0B equity investment is going to be a complete loss.
Readers are
cautioned that while the forecast of dividends does show substantial earnings
increases over time, which may encourage them to think the subsidy is
temporary, be aware that the Muskrat Power Purchase Agreement (PPA) payments are
rigidly set to escalate at a near identical rate. If electricity rates are to be held to
inflation to protect ratepayers, the higher dividends are needed to meet the higher
PPA payments. The $400M subsidy is
likely a permanent requirement.
Mega-Debt: The True Cost of Muskrat
The Province’s
$4.0B equity investment has bigger problems than just being written off without
payback, as terrible as that is.
Government
is already deeply in debt and the Muskrat equity has been issued by increasing
government long-term debt. During the project
construction period, this debt adds new interest costs on itself – more money
is then borrowed to cover these interest costs. By the Muskrat start date in 2020, the
cumulative interest cost on the Muskrat equity is likely to be in the
neighbourhood of $500M.
This $0.5B extra
cost within the Treasury is a nasty hit but there are far more costly burdens
waiting to happen. Absent dividend
income to pay back the equity investment, a complacent Government will simply
borrow more money to pay the subsidies and the growing annual interest costs.
Long-term financing interest cost sensitivity is huge. The difference between the interest and
inflation rate is key to estimating overall present value costs and while
presently the Province’s credit rating may allow it to borrow at the low end of
the interest spectrum shown, the premium over inflation will rise substantially if the credit rating
declines as it surely will.
The chart
following summarizes the estimated present value of the subsidy and the lost
equity. The low end 2% interest premium
range is not truly credible for the long haul.
A net loss of $50B or greater would be quite possible.
Severe
Societal Consequences
The impact
on the Province and all citizens of a $50B loss is largely beyond the scope of
this analysis. One thing is for sure: other program spending in all Government line departments will be
severely squeezed.
Government can’t go on as the big spender and the big borrower. The Muskrat PPA and contracts are entirely inflexible – Government must contribute whatever subsidy is required or else default and lose everything. A Government committed to subsidy will instead look at its spending and would be compelled to slash and burn everything else and raise taxes and fees to untested levels.
Government can’t go on as the big spender and the big borrower. The Muskrat PPA and contracts are entirely inflexible – Government must contribute whatever subsidy is required or else default and lose everything. A Government committed to subsidy will instead look at its spending and would be compelled to slash and burn everything else and raise taxes and fees to untested levels.
The implications
are overwhelming and public consideration of such a severe worst-case scenario
is rare. Attempts were made to write
about it here but deleted – the consequences are inconceivably terrible and
there would be better authors to prepare such an overview. As it is not the recommendation of PlanetNL to
go down the road of operating subsidies, it makes little sense to write about
how terrible that might be anyway.
As very
capably detailed by a recent report of MUN’s Harris Centre, the province
already faces tremendous challenges with aging demographics and the expected population
decline of rural regions (both will contribute to energy sales decline by the
way). Those challenges multiply under
the weight of long-term Muskrat subsidy and loss even if not to the magnitude
of $50B if a loss-saving intervention should occur to the project.
The Harris
Centre researchers might wish to consider revisiting its models in their next
revision to include a considerably harsher economic scenario than they have
allowed for. One key area to explore is the
effect on the Avalon where presently they presently predict modest growth in
the next two decades. As the center of
Government and the principal economic region it stands to reason that it would
have the most to lose when Government is forced to enact harsh budget austerity
measures to slow the growth of debt. The
Avalon region could conceivably suffer the worst impact of all if the
researchers input the appropriate variables into their model.
Final Scene
Completion
and operation of the Muskrat project ends in two alternative outcomes.
The first is
overwhelming pressure on ratepayers leading to the bankruptcy and loss of NL
Hydro and all Nalcor-LCP subsidiaries and their assets – a terrifying prospect
in itself.
The second
is long term operating subsidy leading to the horrifying financial ruin of the
Province and many of its people.
Neither can
be allowed to happen.
The real
alternative needing urgent consideration is how to end this useless nightmare of
a public utility project.
Next Post
The complete
financial write-off and cancellation of the project is presented. It’s no free ride but it’s the least worst
alternative.
References and Reading Material
Muskrat
Falls Project, Sources and Uses of Funds, Issued by Nalcor, August, 2017 (see image file below)
ATIPP RFI Dividend Forecast, Issued by Nalcor, Aug.31, 2017 (see Response to ATIPP Request PB/555/2017 file below)