Monday, 30 January 2017

MUSKRAT COST ESTIMATES "A COMPLETE FALSIFICATION", SAYS ENGINEER

What would you think, having received these comments from a long time professional engineer on the Muskrat Falls project? He writes:

“I could not put up with falsifying information anymore.

To begin with, the original cost of $6.2 billion on which the project was approved was a complete falsification. The estimate was deliberately kept low below $7 billion, so as to appear favourable relative to the cost of thermal power generation.

The likely costs were known about three years ago, but Nalcor Management kept it a secret, steadfastly denying that there were major schedule delays and cost overruns, until it was no longer possible to hide the true status with the election of a new Provincial Government.

The unit prices used were ridiculously low. The Management at the time knew this.