Written By: "JM"
When the Muskrat Falls story is fully written, the date July 22, 2013 may be given prominence as one of those pivotal moments when Nalcor management ought to have counselled the political leadership to change course on its strategy for Muskrat Falls.
When the Muskrat Falls story is fully written, the date July 22, 2013 may be given prominence as one of those pivotal moments when Nalcor management ought to have counselled the political leadership to change course on its strategy for Muskrat Falls.
On
the morning of that day, the Utility and Rates Board of Nova Scotia (UARB)
rejected Emera’s application for approval of the Maritime Link (ML) stating the
deal had to be sweetened by $700 million to $1.4 billion (Net Present Value);
otherwise the construction of the Link would fail as the lowest cost option for
that Province.
That same afternoon, the Nalcor CEO was advised that Hydro Quebec (HQ) had filed a declaratory
judgment in the Quebec Superior Court requesting clarification on the
interpretation of the 1969 Power Contract. The contract clauses requiring
interpretation by the courts initially appeared routine, perhaps even innocuous
in nature. However, this challenge
threatens the very foundation of the Muskrat Falls business case.