The Uncle Gnarley Blog has a new website. Click here to visit www.unclegnarley.ca to view the latest posts!

Thursday, 11 September 2014

VISION BUILT ON DELUSION (PART II)

Written By: "JM"

When the Muskrat Falls story is fully written, the date July 22, 2013 may be given prominence as one of those pivotal moments when Nalcor management ought to have counselled the political leadership to change course on its strategy for Muskrat Falls. 

On the morning of that day, the Utility and Rates Board of Nova Scotia (UARB) rejected Emera’s application for approval of the Maritime Link (ML) stating the deal had to be sweetened by $700 million to $1.4 billion (Net Present Value); otherwise the construction of the Link would fail as the lowest cost option for that Province.  

That same afternoon, the Nalcor CEO was advised that Hydro Quebec (HQ) had filed a declaratory judgment in the Quebec Superior Court requesting clarification on the interpretation of the 1969 Power Contract. The contract clauses requiring interpretation by the courts initially appeared routine, perhaps even innocuous in nature.  However, this challenge threatens the very foundation of the Muskrat Falls business case. 

Nalcor later surrendered to the entirely predictable demands of the UARB in a revised offer called the “Energy Access Agreement” (EAA) which committed virtually all Newfoundland and Labrador’s surplus power to that Province at a price set by auction in the New England States.  This capitulation by Nalcor secured one of the pre-requisites for the Federal Loan Guarantee.  However, in doing so, Nalcor precluded the future allocation of firm power and energy from Muskrat Falls from use for new industrial requirements in Labrador. It also undermined an early argument used to justify the project.

It bears stating that Nalcor did not even possess the wherewithal to negotiate a basement selling price, matching the minimum value the UARB sought in its analysis of Nova Scotia’s lowest cost option.  It is a critical error; one that will cost NL taxpayers dearly should New England prices further deflate due to the continued expansion of the US shale gas industry. 
Is it any wonder that Nova Scotia opposition to the project has been silenced?     

Such a convenient and expedient fix was not available to Nalcor to address Hydro Quebec’s legal action.   Instead there remains a legal uncertainty over the project, as Nalcor continues to spend billions under the waning argument of the ‘lowest cost alternative’. 

Nalcor has been coy about the impact of losing the judgment in the Quebec Superior Court.  The Corporation has publicly argued that the Water Management Agreement is not in jeopardy; that whatever the outcome of the legal challenge , it will have no impact on the Muskrat Falls project..  However, Nalcor has provided sparse detail to substantiate its claim, conveniently declining to speak about the specifics of the case while it is before the courts. 

The public should not be naive enough to accept Nalcor’s claim.  This court challenge of the 1969 Power Contract is very relevant to the Muskrat Falls business case.  The terse response from Premier Dunderdale on the day news of the court challenge broke perhaps reflected the true uncensored opinion of Nalcor’s leadership in response to Hydro Quebec’s initiative.  It was Dunderdale in full nationalist form, the magnitude of this threat to the ‘plan’ was demonstrable by her frustration.   

Make no doubt this court case will have an impact on Nalcor’s overall business plan and energy marketing strategy.  It is a big deal which was duly acknowledged within Nalcor's 2014 Strategy document:  


Stripped to its essence, the challenge is one in which Hydro Quebec seeks judicial clarification that CFLCo cannot take more than 300 MW from the Upper Churchill facility for sale to any third party, pursuant to the recapture provisions of the 1969 Power Contract. If upheld, it will limit Nalcor’s current practice of temporarily “storing” the remaining RECALL energy in the reservoir, producing the energy when prices are highest in the US market. 

More importantly to the NL ratepayer, an unwelcome judicial outcome may also be interpreted in a manner such that CFLCo cannot produce ‘stored energy’ for Nalcor under the terms of the Water Management Agreement beyond the 300 MW limit.   The reader should note that CFLCo is owned by both Nalcor and Hydro Quebec.  In a legal context, Nalcor and its other subsidiaries are defined as “third parties” under the application of the 1969 Power Contract.  

Stated another way, any limit on ‘stored energy production’ would gut the effectiveness of the Water Management Agreement.  It would eliminate the very tool Nalcor must have, in order to meet its firm capacity commitments to the Island, industrial customers, and to Nova Scotia. It would potentially jeopardize the reliability of the electrical system post-commissioning of the interconnection to Labrador.  Ultimately, it would result in higher costs to rate payers. 


In the absence of any substantive analysis by Nalcor, the remainder of this post will attempt to explain the risk of an unfavourable ruling from the Quebec Superior Court:   

1.     Muskrat Falls is what is commonly described a “Run of the River” hydroelectric facility.  The Muskrat Falls reservoir has a live storage capacity of 50 million cubic meters; the figure represents 0.2% the size of the Upper Churchill reservoir.  The limited ability to store water means Muskrat must produce energy when the water runs.  When flows are less than optimal, production is dependent upon the water flows released from the facility upstream.

2.      In 2009, Nalcor submitted a Water Management Agreement (WMA) to the Public Utilities Board (PUB) for approval.  The WMA is intended to optimize production from both Upper Churchill and Muskrat facilities on a year round basis.  Both plants need to be used in combination in order that the Labrador Island Link can provide 900 MW on an “as required” basis for extended periods of time. 

In simplest terms: when the water flows at Muskrat Falls are high, and the Nalcor demand for energy is low, the surplus generation is used to meet CFLCo’s obligations to Hydro Quebec.  The water flow at the Upper Churchill is reduced accordingly.  Any energy produced by Muskrat Falls to meet the CFLCo delivery is “banked” as water stored within the Upper Churchill reservoir.

Alternatively, when the flow at the Muskrat Falls plant is insufficient to meet Nalcor’s demand, the Upper Churchill plant production is increased.  The production will draw down the “banked” energy.

Assuming that the extra production from the Upper Churchill is assured under the mechanism of the WMA, Nalcor can guarantee that 824 MW will be produced to meet the rated nameplate capacity of the Muskrat Falls plant.  In combination with the remaining 80 MW of RECALL power in winter 900 MW is available for transmission over the Labrador Island Link.  It is fairly simple to manage the water flows in this fashion and although it is integral to Nalcor’s planning, following the commissioning of Muskrat Falls, CFLco’s ability to implement the plan is being legally challenged.  The Quebec Superior Court may declare it contrary to the intent of the 1969 Power Contract.

3.    Without the Water Management Agreement there may be times when production from the Muskrat Falls plant is minimal.  If output from the Upper Churchill plant is at the lowest contractual limit of 1200 MW, the resulting production from Muskrat Falls from the water flow would be less than 200MW[i].

4.  Based upon the example in part 3, above, over 700 MW of additional power may be needed from the Upper Churchill facility under the WMA to provide an equivalent production of 900 MW to be delivered to the Labrador Island Link.

5.     The WMA respects the terms of previous power contracts.  Previous contracts such as the 1969 Power Contract, and the GWAC take precedence.



6.     The 1969 Power Contract between CFLCo and Hydro Quebec has language limiting the maximum amount of Power which can be recalled by CFLCo to sell to third parties.  This quantity is withheld from “the power and energy agreed to be sold”.  



7.     Of the 300 MW of recall power there is approximately 80 MW of remaining capacity in winter when all domestic requirements are met in Labrador. 

8.    Under the Administration of Premier Frank Moores, an attempt was made to increase the recall provision from 300 MW to 800 MW under the terms of the 1961 lease agreement.  The attempt failed in both the Newfoundland and Quebec Courts.  A subsequent Appeal to the Supreme Court of Canada (SCOC), upheld those decisions; maximum recall from the Upper Churchill Facility remained at 300MW.

Given the Court Decision described in Part 8, it may be apparent why the SCOC Decision on the interpretation of the 1969 Power Contract is so important.  If CFLCo cannot sell more than 300 MW to a third party, it means in periods of low water flow at Muskrat Falls, only 80 MW of available RECALL power is available to be added to meet Island demand. 

If the Quebec Courts uphold this extreme interpretation of the 1969 contract there could be extended periods where the power available over the Labrador Island Link is ~280 MW, and not the 900 MW which has been assumed by Nalcor.  Although it would not materially impact the total amount of energy produced each year by Muskrat Falls, the energy may not be available when we need it!

What are the impacts of such an outcome?  They are considerable:

1.     Nalcor must still meet the contractual requirement of 167 MW to Emera as part of the Nova Scotia Block.

2.     The Muskrat Falls Power Purchase Agreement (PPA) stipulates that the available capacity (in MW) is limited, firstly, by the contractual obligation to Nova Scotia and, secondly, by the terms of the Water Management Agreement.  Put succinctly, if the Courts uphold Quebec’s legal challenge, the Muskrat Falls PPA guarantees only 110 MW of firm dispatchable power out of the nameplate capacity of 824 MW.  This excerpt from the Muskrat Falls PPA applies:

3.     110 MW is clearly far less than the 675 MW, recently quoted by Nalcor, as reliable firm capacity from the Labrador Island Link at Soldiers Pond.  In the context of issues raised in Part I of this Series, that amount of power is less than 15% of the firm capacity, assumed by Nalcor, in the lowest cost analysis used at DG2/DG3 decision gates.  




4.  If the firm generation is not guaranteed from Labrador, additional generation capacity will be needed on the island to meet the required reliability targets.  The most obvious option would be the continued and long term dependence upon the Holyrood thermal station.  If Nalcor implements the upgrades which are assumed a requirement for the isolated option case, $600 million of CAPEX is required to maintain Holyrood as a long term source of capacity. 

5.    Pursuant to the 1969 Power Contract, Hydro Quebec may elect to take all its allocated energy, per month, in the first or last 20 days.  This implies there is a potential for minimal water flow for up to 10 days duration.  Not only is there potential for Holyrood to be needed as back up generation, it may be required for prolonged periods to meet base deliveries.  The resulting fuel charges would be larger than those assumed by Nalcor, in its lowest cost analysis, and completed as part of DG2 and DG3.  The incremental fuel costs would be much higher than any offsetting energy exports, resulting in net negative impact to domestic rates.       
   
These questions are now being asked by Interveners within the ongoing PUB investigation into the reliability of the Island’s electrical system.  True to form, Nalcor has attempted to limit the PUB from examining these critical issues. It deems this legal risk outside the scope of Phase II of the investigation dealing with issues relating to security of supply after Muskrat is commissioned. 

I am hopeful this Post will document why Nalcor’s position is completely without merit. 

Despite Nalcor’s attempt to thwart review of the WMA, the PUB would be negligent to not include this legal risk as part of its ongoing investigation.  The interpretation of the 1969 Power Contract is an essential element to understanding the reliability of our generation system post-Muskrat Falls.  These issues cannot be decoupled or examined on a selective basis. Although the interpretation presented in this paper is severe it is, in the opinion of the Author, one of the possible outcomes. 

Nalcor must be challenged to explain to the PUB the implications of a Court Decision that 
sides with Hydro-Quebec.  While one must respect that the issue is currently before the 
Quebec Superior Court, the PUB assessment need not be public but it must be completed.  
As stated by the Electrical Power Control Act this is clearly within the responsibility of the 
PUB to guarantee adequate planning of the provinces electrical supply. 

Failure of the PUB to permit the Grand River Keepers and Danny Dumeresque to ask questions relating to the Water Management Agreement would not only be a failure of public transparency.  It would constitute a failure of the PUB, itself, to fulfil its legislated responsibility.  Indeed, why have a regulatory body if issues of this public importance and interest are not fully investigated?

Part I of this series describes the false inputs which Nalcor used in its DG2 Reference to the PUB and third party reviews by Navigant and MHI.  The author would describe it as strategic.  My old friend, Uncle Gnarley, would more likely describe it as deception. 
When the risks associated with the failure of the Water Management Agreement are considered, it is not difficult to see the Nalcor decision to proceed without legal certainty was perhaps delusional. 

“Deception and Delusion” is a concept familiar to those who have read the the recent Oxford Paper by Ansar and Flyvbjerg, et al.  The next and final part of this series will draw a parallel between the conclusions in this research, and what has unfolded on the Lower Churchill project.  I would encourage readers who are interested to spend the 10$ to download the Oxford paper.  It is well worth the read.  



[i] The reader can find further clarification on this from the 2009 application to the Public Utilities Board.  Section 3.1 of the prefilled evidence explains the various extreme situations on how the Gull Island reservoir would respond depending upon the delivery of water from the Upper Churchill.  Within this pre-filled evidence Nalcor concluded that without the WMA there would only be 400 MW of firm output from the Gull Island facility from a rated nameplate of 2250 MW.  Using a similar analogy the firm production from Muskrat Falls would be less than 200 MW in periods of low water flow. 
_________________________________
Editor's Note:  
VISION BUILT ON DELUSION (Part II) was written by "JM".  He is the anonymous researcher and writer who presented a major Paper to the PUB Review during the Muskrat Falls Review.  JM has written a number for Uncle Gnarley Blog, including, most recently, The Snow Job (Part I).  Others include: Gnarley's Theory of Political Devolution and The Great Revolutionary From The Shore and The Right Side of History

JM has also submitted to the PUB a Paper entitled:  Underestimating Peak Load and The Potential Impact On The Muskrat Falls Solution

A full list of JM's Papers can be found on the The Sir Robert Bond Papers Blog by Ed Hollett

To readers who may be unfamiliar with "JM", I would say that, while circumstances require his anonymity, you will be impressed with the depth of his analysis on many aspects of the Muskrat Falls Project. 

- Des Sullivan