The Uncle Gnarley Blog has a new website. Click here to visit www.unclegnarley.ca to view the latest posts!

Thursday 18 September 2014

DELUSION AND DECEPTION (PART III)

Written By "JM"

The New York Times recently published an article "Large Dams are Just Not Worth the Cost".  The opening line foreshadowed the main message of the article:

THAYER SCUDDER, the world’s leading authority on the impact of dams on poor people, has changed his mind about dams
Now in his 80’s, and after a lifetime of promoting large dams, Mr. Scudder has had a Gus Etchegary type of enlightenment.  He is now preaching caution against an industry that he spent his life promoting.  He was compelled to go public with his revised assessment after reading the Oxford University study released in March of this year.

The Oxford Paper, written by economists Ansar, Flyvjberg, Budzier and Lunn, is well worth the $10 purchase price for any person who is interested in public policy based upon mega-hydroelectric development.  It is especially relevant for those who want to assess the record of the Muskrat Falls project in a global context.  

The paper reviews the record of large dam construction on the basis of cost overruns, schedule variance, and overall benefit to the economy of the host countries. It is rich in historical references, and global context.  Had the research been available during the Muskrat Falls debate it would have provided an evidence based comparison with the performance of similar projects and provided a much needed challenge of Nalcor ’s billing of the project.   

The Authors of this Paper have reached the following conclusions:

1)      3 out of 4 dams experienced a cost overrun.
2)      Actual costs are, on average, 96% higher than estimated costs; the median is 27% higher than the initial budget.
3)      The evidence is overwhelming that costs are systematically biased towards underestimation at the original budget.
4)      Eight out of every 10 large dams suffer a schedule overrun. 
5)      Actual implementation schedule is on average 44% (or 2.3years) higher than the estimate with a median of 27% (or 1.7years)
6)      Like cost overruns, the evidence is overwhelming that implementation schedules are systematically biased towards underestimation in the initial planning stages.


How does the current performance on the Muskrat Falls project compare to the findings from the Oxford Paper?  Considering that Nalcor made the decision to proceed with Muskrat Falls at DG2 in November 2010, the cost data from this period of time should be used as the baseline data.  The following table shows the evolution of the cost estimates.  This is the data Nalcor presented to the public with the recommended escalation and contingencies included.  Nalcor deliberately omitted inclusion of “Interest During Construction”.



Based upon the DG2 budget, there has been a 42% increase in that estimate. The figure is comparable to the conclusions reached within the Oxford Paper.  Of particular concern, the element of the project furthest advanced (i.e. the MF to CF transmission line) has more than doubled the 2010 estimate.  Is this a foreshadowing of what is yet to come?

Nalcor has acknowledged a 13 month slip in the schedule for production of first power since the project was first presented to the PUB.  The delay echoes the candid view of the Independent Engineer's November 2013 report which states: 


Nalcor and the Government of Newfoundland have tried to put a positive spin on the under delivery to date.  They have stated that the cost and schedule overruns are similar to those on other mega projects in Newfoundland and are the result of a white hot economy.  Yet, placement of some 700,000 m3 of concrete has only just begun.  There remains much further opportunity for cost over-runs and schedule delay, too.  We should remain concerned! 

The question ought to be asked: why were the over-runs not included in the original cost estimates in the form of higher contingency allocations?  The other resource projects, currently underway in Newfoundland, were certainly known in 2012.   Pressures on costs and availability were easily predicted by anyone familiar with the Newfoundland construction industry.  This risk was clearly identified by many in public submissions to the PUB.  So, why was Nalcor’s contingency allocation so low?   

The Oxford Paper has fascinating commentary that hydro dams often advance due to biased decision making by the proponents:


Our approach to address the debates about whether or not to build dams is to incorporate an evidence-based perspective that reflects how decisions among alternative options are actually made and on what basis.  Theoretical and empirical literature on decision-making under uncertainty proposes two explanationspsychological delusion and political deceptionthat suggest decision - makers' forecasts, and hence ex ante judgments, are often adversely biased



The Authors argue that experts (e.g., statisticians, engineers, or economists) and laypersons are systematically and predictably too optimistic about the time, costs, and benefits of a decision.  With the power of hindsight, does anyone doubt that the management of Nalcor fell into this trap in planning Muskrat Falls? 

The Paper argued that optimistic judgments are often exacerbated by deception, i.e. strategic misrepresentation by project promoters (Wachs, 1989; Pickrell,1992; Flyvbjergetal.,2002, 2005, 2009). Recent literature on infrastructure delivery finds strong evidence that misplaced political incentives and agency problems lead to flawed decision-making.

This paragraph succinctly summarizes why I was so initially opposed to the Muskrat Falls project!

First, Nalcor’s initial decision making was not driven by an unbiased and objective review of all options to meet our energy requirements.  In July 2010, Nalcor made the decision to change the scope of the Lower Churchill Project team from that of energy export (Gull Island) to meeting the domestic demand of Newfoundland and Labrador (Muskrat Falls first).  With this change, Nalcor did not modify its Gated Management Process to reflect the new mandate of meeting domestic supply.   

In reality the project should not have passed DG2 until all options were examined, and Muskrat Falls was selected based on the lowest cost criteria established by the rule of law (Electrical Power Control Act-1994).  This lack of compliance with the rule of law was presumably endorsed by the Government of the day.  The endorsement was either the result of indifference or ignorance of the legislative requirement for the lowest cost criteria.  

The Canadian Environmental Assessment Agency (CEAA), as part of the Joint Review Panel, was first in publically identifying the flaw in Nalcor's decision making process:



Following this damming recommendation from the CEAA, and public pressure by David Vardy, Ron Penney and others, there were efforts by Nalcor and the government of Newfoundland to validate the project to public scrutiny.  The following actions were completed:

1)      Independent Review by Navigant in September of 2011
2)      Reference to the Public Utilities Review
3)      Review by Manitoba Hydro of the Muskrat Falls project to meet decision gate 3, and prior to the sanction of the project.  This process did include a review of several alternatives to Muskrat Falls to meet our needs.

A second major objection to this project was the influence brought by either Nalcor or the Provincial Government to ‘ring fence’ the terms of reference of these independent reviews.  Whether it was a strategic misrepresentation or just an honest simplification, the various third parties were not permitted to examine the project as it was sold the public.  As outlined within Part I of this series, Nalcor has recently admitted that the reliability calculations, and lowest cost analysis did not include the delivery of energy to Nova Scotia.  The lowest cost option as verified by Navigant, the PUB, or MHI is not what has been presented to the ratepayer.

Nalcor should be held to task to explain why the obligation to Emera of the 167 MW Nova Scotia Block  was excluded from the various analysis.

Finally, as noted by the Oxford Paper, the proponents of the Muskrat Falls project were too optimistic on the benefits of the Muskrat Falls decision.  Whether it was the availability of power for Labrador Mining, the benefits of export revenues, or the closure of Holyrood, both Nalcor and the Government of Newfoundland and Labrador consistently overstated the benefits of the project.  Of course, they have also understated immense risks such as cost over-runs and the Water Management Agreement, as discussed within Part II of this series.

As Muskrat Falls enters its mid game, we should remain concerned that project costs will continue to escalate and that the schedule continue to slip.  The next estimate, anticipated in the Fall of 2014, will be an indicator.

Only time will tell if Ed Martin will one day reach enlightenment like Mr. Scudder.  I wonder if Mr. Martin considers a 42% cost overrun a success?   

_________________________________
Editor's Note:  
DELUSION AND DECEPTION (Part III) was written by "JM".  

He is the anonymous researcher and writer who presented a major Paper to the PUB Review during the Muskrat Falls Review.  JM has written a number of Pieces for Uncle Gnarley Blog, including, most recently, VISION BUILT ON DELUSION (Part II) and The Snow Job (Part I).  Others include: Gnarley's Theory of Political Devolution and The Great Revolutionary From The Shore and The Right Side of History

JM has also submitted to the PUB a Paper entitled:  Underestimating Peak Load and The Potential Impact On The Muskrat Falls Solution

- Des Sullivan