Monday, 28 January 2019

"ANONYMOUS ENGINEER" IDENTIFIES DEVICE USED TO LOW-BALL ESTIMATE

EDITOR'S NOTE: The author of today's article is the whistleblower, dubbed the "Anonymous Engineer", who disclosed – on this Blog - falsification of the estimates for the Muskrat Falls project. That was January 30, 2017 . His comments were recorded in a post entitled Muskrat Cost Estimates "A Complete Falsification". A second post called Muskrat: Allegations of Phony Cost Estimates provided significant additional details of low-balling which ultimately were used to justify the Sanction of a project that has become a scourge on the Province's economy. His alarming assertions have been supported with revelations which emerged from Phase I of the Commission of Inquiry. This article attempts to shed light on an issue that is likely to be assessed during Phase II, often referred to as the Construction Phase. — Des Sullivan


Guest Post by the "Anonymous Engineer"
Impact of Labour Productivity on 
"Base Estimate" for the Muskrat Falls Project 

It is almost two years to the month since I spoke with the host of the Uncle Gnarley Blog, Des Sullivan, and subsequently with Anthony Germain of the CBC Morning Show. At that time I revealed that  the estimates on which the Muskrat Falls project was approved were low balled and falsified. I am confident that those statements were heard at the political level and that they might have influenced the Government's decision to  commence the Inquiry which, of course, I have been monitoring.