Terry Robert’s story is about Ed Martin dissing Astaldi. Martin
thinks that the Company is “largely to blame for the massive cost and schedule
overruns” experienced on the Muskrat Falls project.
The Uncle Gnarley Blog has a new website. Click here to visit www.unclegnarley.ca to view the latest posts!
Showing posts with label Grant Thornton Forensic Audit Report Construction Phase Commission of Inquiry Muskrat Falls Project. Show all posts
Showing posts with label Grant Thornton Forensic Audit Report Construction Phase Commission of Inquiry Muskrat Falls Project. Show all posts
Thursday, 21 February 2019
Monday, 18 February 2019
FORENSIC AUDIT: NALCOR IGNORED BIG EARLY WARNING SIGNS
The Uncle Gnarley Blog has posted two commentaries on the second Forensic Audit Report of Grant Thornton released today by the Commission of Inquiry into the Muskrat Falls Project. Both articles were prepared by Ron Penney, David Vardy and Des Sullivan who have standing at the Inquiry on behalf of the Concerned Citizens Coalition.
This piece contains the key findings of the Forensic Audit. Also posted is a lengthier and more thorough examination of the Report entitled “Evidence of Malfeasance?: A Review of the Forensic Audit Report into the Muskrat Falls Project (Phase II)”. It is available now at the Link. - Des Sullivan
HIGHLIGHTS OF SECOND FORENSIC AUDIT REPORT
As was the case with Phase One of the Muskrat Falls Inquiry, the construction phase of the Inquiry has commenced with the release today of the forensic audit conducted by Grant Thornton.
This piece contains the key findings of the Forensic Audit. Also posted is a lengthier and more thorough examination of the Report entitled “Evidence of Malfeasance?: A Review of the Forensic Audit Report into the Muskrat Falls Project (Phase II)”. It is available now at the Link. - Des Sullivan
HIGHLIGHTS OF SECOND FORENSIC AUDIT REPORT
As was the case with Phase One of the Muskrat Falls Inquiry, the construction phase of the Inquiry has commenced with the release today of the forensic audit conducted by Grant Thornton.
The
audit sets the stage for the examination of witnesses crucial to the
understanding of how the project went so badly wrong.