Guest
Post by Muskrat Falls Concerned Citizens Coalition Members David Vardy, Ron Penney and Des Sullivan
Now
that the second phase of the Inquiry has begun it may be helpful to take stock
of where we are and what we have learned to date.
Here are fifteen key issues on
which the Inquiry Commissioner, Richard LeBlanc, must opine and about which the
public should be informed. We have not attempted to assign priorities to them
but we can say they that, while they are important, there are others issues that have been identified. We will
post them another time.
1. When the Muskrat Falls project was
sanctioned there was only a three per cent probability that the project would
be completed on time, based on evidence provided by Nalcor’s risk consultant
Richard Westney.