The new Hydro President, Jennifer Williams, is either threading very softly with a Furey Government afraid of taking decisions or has already succumbed to Nalcor’s long established culture of deception.
Because Ms. Williams is still new, we can only hope that her comments to CBC last week are matters of misspeak rather than signs of an evolving attitude. There is good reason to be concerned.
CEO Williams suggested to CBC that it is common for new utility infrastructure to experience “growing pains”.
The comment left the impression that those “growing pains” include the major problems currently plaguing the Muskrat Falls project, which are limiting production to around a third of capacity. After spending nearly $15 billion and years behind schedule, growing pains should constitute only the minor problems identified in a punch list audit during commissioning.