Likely everyone
remembers #DARKNL. January 2014 - successive days without power
followed by rolling outages - tens of thousands of people huddled in the cold
and the dark.
It didn’t
sit well with anyone – just ask Kathy Dunderdale.
The PUB initiated
an investigation into the root cause of the power failures. The Liberty Group,
a Consultancy, was hired to conduct the inquiry - which had two phases.
The Phase I Report,
released last year, gave exhaustive details of the poor management culture at
NL Hydro, the dreadful state of maintenance on Hydro’s generating assets, and
the need for more generating assets to enhance reliability – which led to a new
generator (sort of) installed at Holyrood.
The Phase II
Report dealt with an “assessment of the adequacy and reliability of the IIS
(Newfoundland island system aka “Isolated Island Service”) to meet customers' load both up
to and after the interconnection with Muskrat Falls.” It was released August 19th.
Liberty
is quoted frequently in this Post. It is best that this narrative is described in
the Consultant's own words.
That the
investigation occurred at all was a minor miracle. It was supported by Newfoundland Power – somewhat
late to the Muskrat game – their weight critical, nevertheless, to convincing the PUB
serious issues needed further study. Several individuals, some connected with
the 2041 Group, including this blogger, made submissions to the PUB to support
the initiative.
Intervenors
were concerned that a prolonged outage associated with failure of the 1100 KM extension cord traversing several climatic
conditions including over the Long Range Mountains - given that the bulk of the
load was located at the far end, on the Avalon Peninsula - would seriously threaten our economy and society.
Liberty noted
that even with the addition of a new generator “more work will be needed …including
two major features that Hydro is not necessarily considering at this time.
Those features are (1) additional power supply and (2) expanded organizational
capabilities.”
Liberty reminds
us that the outages which occurred in January 2014 “were as much or more due to
organizational issues as they were due to system inadequacies”. The Consultancy
stated that those problems still plague NL Hydro. Having been previously addressed
on this Blog, I will restrict today's comments to the post-Muskrat phase, except
for one.
Liberty Wants More Supply Now
to Mitigate Outages
Liberty
expresses concern that “(w)hile it had long been contemplated that Muskrat
Falls would preclude the need for more supply until the 2030s…new supply will
be needed before Muskrat Falls is in service, to mitigate near-term supply
issues, and after Muskrat Falls is in service, to mitigate the impact of
extended outages of the Labrador-Island Link (LIL).”
The source
of this concern is what the Consultancy describes as “continuing problems with
Hydro’s existing thermal generating units and the delay in the in-service date
for Muskrat Falls increase the risk of outages until the interconnection.”
Liberty
expects that this additional supply can be obtained “through firm purchases, if
available, over the Maritime Link or additional new generation on the IIS”. In
their own words, the Consultancy believes “…the supply risks are greater than suggested by
Hydro’s assessment and that new generation is likely required prior to the
interconnection.”
Liberty’s concern
is not based upon an increase in demand as the Exhibit (below) confirms.
Readers may remember that Nalcor acknowledged earlier this year that Load
requirements will not hit the forecast level used to justify Muskrat Sanction until 2036.
(Given a recent CBC report about consumers converting to oil that date may even
be optimistic – the public broadcaster may want to inquire about increasing sales
of heat pumps, too).
Liberty
warned, in its 2014 Report, that despite the addition of a new generator at
Holyrood “generation reserves are very low and the risk of outages remains high
for the 2015-17 winter seasons.” This concern is now extended because “full power from Muskrat Falls is forecast as “mid-2020”….in time for
the winter of 2020-21 (which) contrasts to the original plans of the winter of
2017-18.”
The risks of
continuing outages relates not to just the bucket of bolts constituting Hydro’s
existing thermal generation but also due to a “…shift to a 90% probability for
the peak demand forecast from Hydro’s previously used 50%.” Liberty takes a
more conservative approach to the winter peaking problem than does NL Hydro.
Hydro, as Liberty discussed in a prior Report, uses outages as a demand management
tool - a practice it condemned. (In fact, the only problem Hydro ever had related to “peak” demand due to the unbridled installation of electric baseboard heating in new (primarily residential) construction which “policy” could have resolved. Nalcor essentially used this “false” problem to
justify Muskrat Falls, ignoring the attendant risks.)
Outages Cannot be Avoided says
Liberty
Post-Muskrat
Falls, Liberty is concerned that the “isolated island system” or IIS is “relatively
small…approximately 1,700 megawatts”, with the majority of its load centered on
the Avalon Peninsula. It states that the size of Muskrat Falls (824 megawatts) …”is
large for the size of the IIS” which “presents challenges from a reliability
perspective given the consequences of the instantaneous loss of the LIL”
(Labrador Island Link) – precisely the concerns over which the small group of
intervenors sought the PUB’s ear - over Nalcor’s objections.
Liberty
points out that “outages cannot be completely avoided”.
Indeed, you
may find the Consultant’s next comments disturbing. Liberty states:
“Reliability analyses completed by
Hydro for the LIL indicate a probability of a full LIL outage every three years
with an average duration of twenty-nine hours.” Hydro believes …customer
outages will be limited to a few hours…” (but) “Liberty believes…that there
will be more LIL …outages than estimated by Hydro”. (emphasis added)
Simply put,
if there is not sufficient backup, there will be additional customer impact,
including rotating outages. The capacity will have to come from “…new
combustion turbines or firm, dependable capacity from Nova Scotia via the
Maritime Link”, says the Consultancy.
Liberty
recommends that Hydro secure the necessary capacity commitments to mitigate the
consequences of an extended LIL bipole (full system) outage. Says Liberty:
“Extended LIL outages are possible,
including failure of the overhead line (OHL). Although Hydro’s stated objective
is to complete repairs for the overhead lines within two weeks, it is difficult to have confidence that two weeks
is the maximum limit for an OHL-related outage, recognizing the magnitude of
the challenge of repairing significant OHL damage in potentially extreme
weather and in harsh terrain.” (emphasis added)
Maritime Link: a 300 MW Generator?
Liberty
states that “Hydro’s reliability analyses assume the Maritime Link is
equivalent to a 300 MW generator with high availability for the IIS.” They note that “(t)he Maritime Link is thus a critical feature for the operation and
reliability” of the province’s electrical grid post-Muskrat commissioning.
Liberty wants
“…additional studies (to) be completed not only with the (Maritime) Link in
service, but also with it out of service”. They acknowledge some of the questions
critics of Muskrat have raised from the beginning – in particular, that “(o)n a
bipole trip (a complete Labrador Island Link failure), Nova Scotia will have to
replace the power it loses from Muskrat Falls and provide additional capacity
for the IIS.”
Nalcor has
never produced an agreement with Emera (which would likely require the approval
of Nova Scotia’s UARB) how the ML will be “a source of dependable generation…”
even after Nova Scotia's coal fired generators are shut down. It need to do just that. This is hardly a minor loose end.
Liberty was
charged with investigating issues of power reliability and security. In this
Study it was not concerned with the cost of those installations.
Yet, Liberty has serious concerns about Nalcor’s outage claims. Its doubts that a bipole
failure on the LIL can be repaired within two weeks. It claims that additional thermal
generating capacity is necessary and that another deal with Emera must be
entertained.
Taken together, Liberty has kicked the last leg, if any remains, out from under the idea Muskrat was a viable option - even as a secure supply - without refurbishing Holyrood, the very asset, Nalcor argued, it was designed to replace.
Taken together, Liberty has kicked the last leg, if any remains, out from under the idea Muskrat was a viable option - even as a secure supply - without refurbishing Holyrood, the very asset, Nalcor argued, it was designed to replace.
None of the “back-up” arrangements proposed by Liberty come for free.
As construction
costs mount and consideration is finally given to the costs of insuring against
a winter outage extending from twenty-nine hours to in excess of two weeks, we
await another of Stan Marshall’s Ed Martin style revisions.
I wonder how many Liberty Reports it would take to convince Danny Williams Muskrat was a dog from the get-go? But, then, it was always all about Danny. Wasn't it?.