Thursday, 20 December 2018

MUSKRAT ENERGY COST – ANOTHER MEASURE OF FAILURE

Guest Post by PlanetNL

PlanetNL22: Muskrat Energy Cost – Another Measure of Failure
Several leading electricity industry research organizations compile annual estimates of utility scale generation options.  These reports roll up the expected lifecycle costs relative to energy output to provide a single energy cost figure known as a Levelized Cost of Energy (LCOE).   LCOE allows alternatives with high capital cost but low operating cost to be directly compared to options with low capital cost but high operating cost.

The energy industry consistently selects projects that can deliver competitively low LCOE numbers, however, Nalcor avoided this technique in favour of a customized and burdensome Cumulative Present Worth analysis that avoided illustrating the true economic merit of Muskrat Falls.  Although the LCOE metric was front and center in the Nova Scotia regulatory hearing for the Maritime Link, it was avoided by Nalcor and Government here.  Little wonder, as Muskrat’s LCOE is nothing to be proud of.