A Tale of Two Regulators
Guest Post by JM
The
government of Clyde Wells introduced the Electrical Power Control Act in 1994.
It was implemented to define electrical power policy in the province and to provide
a means for the utilities to earn a return on their investment in the
generation and delivery of the power. Under
the EPCA the Public Utilities Board (PUB) has broad powers to regulate and
legislative responsibility for the planning of future power supply in the
Province.
It
is worth reading the Act to truly understand the breath of powers which the PUB possesses
in these areas. This did not occur by accident. On the contrary, the
legislation received the very deliberate focus of the premier of the day. When he introduced the Bill in the House of Assembly, Clyde Wells stated:
Since
June 2010, when the decision was made by Nalcor to develop the Muskrat Falls
Project, the PUB should have had an integral role to ensure the project met the
clear “Declaration of Power Policy” as outlined within Section 3 of the
Electrical Power Control Act.
The
process of review ran counter to the intent of the 1994 legislative initiative. Muskrat Falls was conceived in secrecy, and
born under both delusion and deception.
The process was neither open nor
transparent. Sadly, it continues to be
executed in the same manner.
The
people of the province will bear the result of this poor public policy with the
predicted doubling of our electricity rates by 2021.
In
Nova Scotia another tale can be told.
In
2014 the UARB (Nova Scotia’s version of the PUB) was given unfettered authority
to examine and decide whether to approve the Maritime Link Project. The UARB initially thought the price for the
Maritime Link was too expensive and too risky to be borne by the Nova Scotia
rate base. As a result of conditions
imposed by the UARB, the Nova Scotia ratepayer now has first priority access to
the surplus power from Muskrat Falls, at market rates for the power (shredding
one of Nalcor’s rationales for the project - industrial development in
Labrador).
Nova Scotia obtained additional
assurance with respect to over-runs by imposing the condition that Emera must
present and receive approval for any over-runs above the DG3 estimates.
In
Nova Scotia the rate payers have benefited tremendously from the UARB. In fact, the Agency insisted upon delivery of
a deal that for Nova Scotia is superior to the one originally negotiated by
Emera. It successfully exploited Nalcor’s weaknesses to the benefit of the Nova
Scotia ratepayer.
Nova
Scotians have truly benefited from the openness and transparency which
underpins electricity policy in their province.
Now,
the next chapter of Muskrat Falls is unfolding between Nalcor, Emera, and the
UARB.
_______________________________________________________________
Related:
_______________________________________________________________
Emera
subsidiary, Nova Scotia Power, has applied to the UARB for authority to have
the NS ratepayer pay approximately $160 million per year in connection with costs
associated with the Maritime Link’s completion in advance of the flow of power
from the Muskrat Falls Plant.
A recent CBC article incorrectly
stated that the UARB’s approval of those costs within the Nova Scotia rate base
had already been approved. The CBC was also wrong in asserting that the NL
ratepayers “are eating the cost over-runs”.
The
fact of the matter is that the UARB must yet decide what portion of the ~$450
million requested by the Emera subsidiary shall be recovered from the NS rate base. Any amount not approved shall constitute an
overrun – which will be shared by both Nalcor and Emera according to the terms
of the agreements between the companies.
This
is a high stakes application for Emera. The company’s shareholders are exposed
to considerable risk if the UARB does not provide full approval of the
application. Nalcor, too, could be on the hook for over $100 million dollars associated with the delay to the Maritime Link.
It
is an issue which deserves more careful consideration from the CBC and from other
news media.
In
their application, Emera has outlined and attempted to quantify the potential
benefits to the Nova Scotia ratepayer with the early commissioning of the
Maritime Link. These are outlined under four
broad categories:
1) Exported Energy to
Newfoundland and Labrador
2) Imported Energy from Newfoundland
and Labrador
3) Optimization of NS Power
generation assets
4) Enhanced Reliability.
In
support of its application, NS Power has forecast that over 2 TWh of energy
will flow over the Maritime Link from NL between January 1, 2018 and December
31, 2019. They have estimated that the
energy will have a value in excess of $120 million (i.e. 6 cents per Kwh).
In
this province, we need to ask: prior to Muskrat Falls generation, where will
this 2 TWh of energy come from? Undoubtedly,
this energy must be that associated with the remaining RECALL from the Upper
Churchill project.
This
likely source raises many interesting questions. They include:
1) Can the Maritime Link be
put into service without the Labrador Island Link (LIL) and the transmission
interconnection between the Muskrat Falls and Churchill Falls plants (LTA)?
2) If the LIL and LTA are put
into service, will Nalcor make a similar application to the NL PUB to have the
cost of an early commissioning of the island transmission assets included in
our rate base prior to the commissioning of the Muskrat Falls Plant? Will our rates start increasing in 2018?
3) Are Emera looking for
recovery of debt and equity financing fees on the Labrador Island Link as they are
for the Maritime Link? The reader should
remember that Emera owns 29% of the Labrador Island Link.
4) What charges is the
Newfoundland ratepayer expected to pay on the LIL in 2018 and 2019, associated
with the Labrador Island Link?
5) If this 2 TWh of energy is
delivered to Nova Scotia, will Nalcor effectively give it to them, or will
Emera pay market value for this energy?
6) Who will get priority
access to this RECALL energy, the NS or the NL ratepayer?
7) Is it possible to purchase
additional Upper Churchill energy to effectively displace oil generation at Holyrood
and lower our rates in NL?
8) If the Labrador Island
Link is commissioned early for the primary benefit of Nova Scotia ratepayers,
why would NL ratepayers be expected to pay for it?
But
what is best for Nalcor, may not be best for the ratepayers of the province.
In
the current PUB process, Nalcor has not provided any guidance regarding the use
of RECALL to meet our increasing demand, or even to displace oil generation at
Holyrood. Nalcor has provided little guidance about where 300 MW of power can
be imported from Nova Scotia, or if any RECALL power can be used for the
province before or after Muskrat Falls commissioning.
Experts
presenting to the PUB have recommended, in the absence of Nalcor’s guidance,
that plans should be implemented immediately to secure an additional combustion
turbine to ensure adequate system reliability prior to Muskrat Falls. Request for Information “PUB-NP-314.pdf”
contains this citation:
Nalcor
has not yet shared their plans for RECALL power with our PUB. However, in
preparation for Hearings presently scheduled by the UARB, Nalcor and Emera have
filed confidential exhibits concerning where and how the 2 TWh will be made
available to Nova Scotia at the end of 2017.
Unbelievably,
the UARB is privy to information pertaining to positions taken by our Crown
Corporation, related to RECALL power, which our PUB has yet to see!
Nalcor
are trying to reduce their own corporate exposure to Emera. We need to know if
what suits Nalcor is in the best interest of Newfoundland rate payers.
As
Muskrat Falls enters the mid game, it is becoming obvious that Nova Scotia is
the primary beneficiary of the Muskrat Falls project. The projects represents a terrible deal, one
in which NL takes the majority of the risk and Nova Scotia reaps the
upside.
It
will be a sad day in 2020 when the LTA, LIL and ML are commissioned, and the
RECALL power passes by the blasting smoke stacks of Holyrood, to supply green energy
to Nova Scotia. All the while, within
our rate base, we will be paying Emera their return on equity on the LIL - so
that the line can be primarily used to deliver energy to Nova Scotia.
The
time is now to open the doors of NL Hydro. We need the PUB to examine those
issues, just as the UARB is doing for Nova Scotia. Nalcor has obfuscated the truth on this
project since its inception. In the
backdrop of delays to Emera, $800 million dollar over-runs to Astaldi, and a 2-year
delay in the project schedule, the PUB needs to determine what else lurks
behind the closed doors of our Crown owned utility.
Nalcor
are in a very difficult position. I am
sure they believe they are acting in the best interest of the province; as an
early inclusion of the LIL into our rate base may mitigate some of the rate
shock associated with the project, and reduce some reliability related
investments. However, what is certain is that the NL
ratepayer deserves to have the same openness and transparency as they do in
Nova Scotia. There must be some
recognition that we are the ones who are paying for this great Albatross of the
north.
It
is both ironic - and depressing - that the Labrador Island Link will be built, and
likely used to import Upper Churchill power to both NL and NS, long before the
plant at Muskrat ever produces electricity.
It is unfortunate that Nalcor denounced that as a practical option for
our power supply back in 2012, even though there were many who considered it the least risk and least cost option at the time.