This is one engineer's story of how Nalcor "low-balled" the cost estimates for the Muskrat Falls project, paving the way for huge cost overruns. The alleged phony estimates led to an inadequate budget for the project, and indiscriminate contract awards — Astaldi a classic example. The engineer states that Nalcor failed to perform adequate due diligence — ignoring well-established processes designed to confirm valid estimates such as those used by SNC-Lavalin. The post also discusses the implications of those allegations for the integrity of our political process.
Muskrat
Falls — A History of Misinformation — 2010 to 2015
In 2010,
Nalcor hired SNC Lavalin (SNC) to conduct the engineering, procurement and
construction management (EPC) for the MF project. A key aspect of the Company's role —
essential to any decision to proceed — was the preparation of a cost estimate.
The $5
billion investment Premier Williams announced at that time quickly became $6.2
billion ($7.4 billion, including the cost of borrowing) as Nalcor sought
sanction from the Dunderdale Government, in 2012. $6.2 billion was the cost
figure Nalcor used in its Application to the PUB and the claim that the Muskrat
Falls option exceeded the “isolated island” option by $2 billion.
But soon
after the provincial government gave its blessing to the much-heralded legacy
project — given boost amidst fanfare, hyperbole, the pillorying of “naysayers”
and embellishments that included the promise of green power, profits in
the billions of dollars, and an end run around an avaricious neighbour to the
export market — sceptics soon learned that the hype could not be sustained.
The truth
about this project began to trickle into the public domain. While the ugly facts ought to have unfolded
as a flood, it seems they were held back by bureaucrats unworthy of the power
to which they had been entrusted.
Was the lid
kept on the "real" price tag of Muskrat Falls in the interest of
re-electing a Tory Government? Did the exigencies of party politics outweigh
consideration of the public's right to know? Was it the case that Nalcor and
the government couldn't care less that the project was a bust before it got
started?
Now, left
for digestion is the source of the falsification of the original project
estimates in consequence of an $11.7 billion price tag — heading for $15
billion, according to many expert engineers.
But this
digestive process is important. It may be beyond the public's capacity to stop
the madness, but we have a right to assess the ethical standards of those who
contrived it.
Last week,
in a post entitled Muskrat Cost Estimates: A Complete Falsification a
well-placed former Professional Engineer with Nalcor made this comment:
“I could not
put up with falsifying information anymore.
To begin
with, the original cost of $6.2 billion on which the project was approved was a
complete falsification. The estimate was deliberately kept low — below $7
billion, so as to appear favourable relative to the cost of thermal power
generation.
The likely
costs were known about three years ago, but Nalcor Management kept it a secret,
steadfastly denying that there were major schedule delays and cost overruns,
until it was no longer possible to hide the true status with the election of a
new Provincial Government.”
The
engineer’s claim of falsification of the estimates mirrored those made by other
professional engineers who played key roles in the project. But this
professional gave details of a level of deception that exceeded that heard from
any other quarter.
Following
additional interviews, more details have emerged alleging that the early
project estimates were phony.
The evidence
disputes the assertion by the new Nalcor CEO, Stan Marshall, who appraised the project this way: “It was a gamble. And
it has gone against us.” Obviously Marshall was trying to invoke a “risk”
metaphor. He could simply have said that the sanction decision was the equivalent of
going for broke.
Fictitious
project estimate met pre-determined project cost
Many
engineers who are specialists in their field possess specific knowledge of the
processes which their profession has developed to ensure that owners do not walk blindly
into foolish investments. Some of them now ask: who signed off on the
"Approved for Implementation" cost estimate? Did SNC “sign off”? Was
proper due diligence exercised?
The evidence
surrounding those questions, and the alarming acceleration of cost overruns, is
disturbingly inconsistent with what they consider to be due diligent practices.
The Uncle
Gnarley Blog’s engineering source has now confirmed that SNC-Lavalin was
engaged in the preparation of cost estimates for the project, but that the
company did not issue one “Approved for Implementation”.
Within SNC-Lavalin, an "Approved for Implementation" cost estimate necessarily
follows an “Executive Review” of the numbers. These are rigid processes
essential to concluding a project’s viability — which conclusion, of necessity,
must be matched by an “implementable” budget estimate.
Engineers
state that an Executive Review is an essential and integral part of SNC’s
"Estimate Validation Process."
For a
multi-billion dollar project, the executive review panel — whether of SNC or of
any organization — typically consists of the VP of Project Management, VP of
Construction, VP of Design Engineering, VP of Finance, and VP of Risk
Management.
This
engineer explains that the group’s knowledge and experience coalesces in an
effort to dissect the estimate, and requires that the team charged with
preparing it is faced with the highest level of scrutiny. They are expected to
defend the source and validity of the information, the integrity of the unit
prices, the construction methodology, the project schedule, the risk analysis,
and the proposed contingency allocation.
The process
could take a week to ten days for a multi-billion dollar project.
Upon
completion of the review, any errors and omissions are corrected — and only
then does the "Executive Panel" endorse the estimate.
In the
absence of such a review, major errors can (and do) creep into an estimate with
catastrophic consequences.
In the case
of the Muskrat Falls project, the problem of the budget dated back to 2012 when
Nalcor learned that the cost estimates — prepared by SNC — were not compatible
with the “Scope” of the project. Said the engineer: “we were satisfied on three
levels:
- Scope of the project — well defined,
- Engineering — major parameters
completed,
- Quantities changes — minimal.
But the
fourth — the budget process — was a catastrophe.
And this was
not due to a lack of knowledge.”
“Nalcor
knew”, he said, “that there was a major gap in the project scope vs. the
estimates. Nalcor simply took a policy decision to understate the project
costs.” As a result, the budget allocation for the project was also inadequate.
Low Project
Estimate led to low (wrong) Budget estimate which led to…
With the
project estimate wrong, the budgets associated with the work contracts were
also wrong. “They were,” noted the engineer, “almost always too low.”
He states
that, from the moment project construction implementation began, the bids
received were so much higher than the project budgets approved by Nalcor that
the crown corporation was forced into "creative accounting on a massive
scale”.
The
contrived low budgets inevitably meant that the bids for the contracts far
exceeded the budgets. This was an immediate cause of major project cost
overruns.
It appears
that no “Executive Review” was ever done; if it was, he stated, how such errors
could go undetected remains a mystery.
Having
low-balled the estimates, Nalcor staff soon had to deal with the bids for
various pieces of the work.
The engineer
states that "the sufficiency of the budget appeared to be the only
criterion when awarding a contract."
“Contractor suitability”, he said, “took a spot that was a distant second.”
“Contractor suitability”, he said, “took a spot that was a distant second.”
The
engineer’s comments provide readers with a glimpse into why diligently prepared and
tested (defended) cost estimates for the Muskrat Falls project were so
critical. They partly explain the project’s current cost estimate of $11.7 billion; the other part relates to the project team’s inexperience and incompetence.
The massive figure also provides insight into Nalcor’s settlement with Astaldi
of a $700 million claim for “extra” costs.
The Astaldi
Fiasco
The engineer
noted that the Astaldi contract was a classic example of how Nalcor dealt with the
insufficient budget and the low-balled estimate.
Demolition of the "Dome" |
Said he:
“Here was a contractor who had never worked in Canada, had no experience
working in a harsh environment like Central Labrador — its senior management
never having seen a snow storm. The Company had no idea about low productivity
winter work, no knowledge of managing labour under the kind of labour contract
Nalcor had entered into with the trade unions. Yet, it was awarded the most
critical contract of the whole project simply because the bid fit Nalcor's
budget for the work.”
As if to
underscore the point, he continued: “The Unit costs were so wrong… it did not even include
consideration of our cold weather environment… such estimates should be in a
class by itself… you could see from going through it the bid was so
wrong… because it had so many things left out. The Canadian contractors knew
what they were doing. They were hundreds of millions of dollars higher than the
Astaldi bid.”
The short
list — some bidders had joint venture partners including Canadian firms —
contained four bids for the powerhouse, spillway, and transition dams. The
highest bidder was the Salini joint venture $1.9B, followed by IKC-ONE
partnership $1.7B, Aecon partnership $1.55B and Astaldi $1.0B.
The three
highest bidders might be expected to be close given their prior experience on
heavy civil projects. And in the context of the size and nature of the tender,
they were within striking distance of each other’s bid — that is, except for
Astaldi.
Our current
engineering counsel gave the Astaldi problem additional context.
Normally, he
stated, when such a gap occurs in the bid prices received, a prudent owner will
ask why the big difference. Did the lowest bidder fully understand the project?
What, if anything, was missed? In particular, the owner might ask: why were the
three experienced bidders so much higher than the lowest — the latter having
the least to bring to the table?
Said the
engineer: "If Nalcor noticed it, they ignored it. The evaluation and award
was done behind closed doors with the highest secrecy. Every contract
functioned this way, to a greater or lesser degree."
The
Executive Management of SNC left the project in late 2012. SNC’s continuing
involvement was principally associated with the project’s engineering design.
Nalcor, in
spite of being complete novices (virtually all the management team had come
from the oil industry) brought down the “curtain” on SNC’s substantial hydro
project expertise and did not find it elsewhere. Nalcor took not just the
enormously complex job of procurement and project management in-house, it took
full control over the entire estimating exercise. Nalcor proceeded with what it
perceived was a “saleable” $6.2 billion figure — even though, the engineer
noted, "everyone knew" it was completely unsustainable.
In that way,
Nalcor kept control of the project cost estimates and the assumptions on which
they were based, allowing aggressive “unit pricing”, a low contingency, and
other tricks of the trade to low-ball the estimate and maintain the fiction
that Muskrat was “the lowest cost option”.
Falsified
Forecasts Hidden for Three Years
Nalcor
controlled the public narrative — choosing what the public was allowed to learn
and when — until the low-balled figures could no longer stay hidden beneath the
lie amid fast-rising project costs.
Stated the
engineer: “Obvious was
the chronic shortage of the amounts budgeted for each contract — hence the
compelling need to falsify the forecasts — until the Provincial Government
changed."
Finally
Since 2012,
costs have risen on the Muskrat Falls project by $4 billion. In announcing that
project costs had ballooned to $11.4 billion in June 2016, the CBC attributed
this comment to the current Nalcor CEO: "I'm not at all surprised that the
cost is where it is," said Marshall, adding the "original estimates were
low."
CEO Stan Marshall |
Was Mr.
Marshall telling all that he knew? Is he still content with that explanation? Or, is it just standard industry to falsify project estimates to get the project approved even at the risk of getting the owner in trouble?He might wish to address his remarks again.
This blogger
is not in a position to verify the allegations made here. I can say that the
informant was forthright in answering my questions and that his integrity seems
unassailable. This is a case of one of Nalcor’s own, now no longer in its
employ, explaining to a concerned public why a project on which their hopes and
expectations were raised to a high level has crashed to earth. By any measure,
what he has to say has major implications for the public, for the public purse,
and for the integrity of government.
But there is
more.
This
engineer’s allegations also have enormous implications for politics at the highest level of this province. Readers are reminded of the comment that the
falsification of the project estimates persisted “until it was no longer
possible to hide the true status with the election of a new Provincial
Government.”
If nothing
else, the engineer’s comments place a major cloud over the integrity of our
political system and of our political leaders.
Perhaps the
mainstream media will ask some of the disturbing questions this story evokes.
Perhaps they
won’t.
Premier Dwight Ball |
But if the
allegations are true, the public deserves to know if former Premiers were party
to, and aided in, the deception. Did successive Progressive Conservative Administrations play a role in suppressing
low-balled project estimates and huge project cost overruns in an attempt to
secure the election of 2015?
Government
at all levels — bureaucratic and political — must be held accountable. We need
to know if this engineer’s allegations are correct.
Premier
Ball, CEO Stan Marshall: the people of Newfoundland and Labrador deserve those
answers right away.