Thursday 31 March 2022

MUN ELECTRIFICATION: A FORMULA FOR POLITICAL AND ACADEMIC STUPIDITY

Guest Post by PlanetNL 

PlanetNL42: Electrification at MUN + Broken LIL

A Formula For Political and Academic Stupidity

Government announcements issued on Friday afternoons are almost certainly bad news disguised as good.  Government will try to spin only the positives while the media and public must figure out the negatives.

So it was this past Friday when much enthusiasm was fawned over the planned conversion of Memorial University’s central heating plant from oil to electricity.  Provincial, Federal, and Memorial representatives lauded the emissions reduction that would result from 10.5 million liters less fuel consumption at Memorial. The $10.5M project will be funded 50/50 by Federal and Provincial programs specific to reduction of greenhouse gas emissions.  All that sounds great - there couldn’t possibly be any downside, could there?

Well, what if reducing 10.5 million liters of diesel consumption at Memorial requires the Holyrood Thermal Generating Station to burn 30 million more liters of heavy fuel oil, resulting in far worse provincial emissions and increased cost to ratepayers?  That’s the kind of info that does not get mentioned at these cheerleading events. 

When Will Muskrat Power Truly and Fully Arrive?

To succeed, electrification initiatives to reduce emissions need green energy to replace fossil fuels.  The new source of green energy in this province is supposed to be Muskrat Falls hydropower delivered to the Island by the Labrador Island Link (LIL). 

That would be the same LIL whose construction was essentially complete back in 2017 and has since been plagued by alleged software design problems.  It has operated at an average of about 10% of it’s rated design capacity and is normally either out of service altogether or whatever is available is shipped off to meet contractual commitments to Nova Scotia.  The share of energy used on the Island has been miniscule.  After five years of endless failure, utility and government officials refuse to admit this is a lemon of their own making. 

The only serious appraisal of the situation has come from the Public Utilities Board US-based consultant, Liberty Consulting Group. Liberty’s latest quarterly report, issued on March 11, stated they have no idea when, if ever, the LIL will operate as intended.  They stopped just shy of saying what has become obvious: that if the project is left in the hands of the same set of managers who have repeatedly failed to date, we should expect it will never work.

The evidence regarding the dismal prospects for the LIL are quite plain to see.  It is simply not reasonable to expect that green energy from Muskrat will be available to supply the new Memorial electric boilers in the foreseeable future.  Extra winter season electrical power will instead have to come from the same place is has for decades: Holyrood. 

Irrespective of the source, it may remain true in the narrowest sense that Memorial will not burn oil on their own property and may therefore lay claim to becoming a greener campus, keeping up with their mainland and global competition in being able to boast they are greening up their operations.  The claim is however a total farce if the utility is forced to burn fuel to meet this new electricity demand – in fact, far more fuel than Memorial expects to save.

Memorial University Heating Plant

Major GHG Reduction Backfire

A few more facts expose the magnitude of the risk that the politicians and Memorial executives fail to recognize.

First is that Holyrood is a rather inefficient generating station that converts only 30-35% of fuel energy into electricity.  Contrast this to a heating plant boiler system such as Memorial’s that typically turns 75% or more of the fuel energy into usable heat.

You don’t need to be an Engineering Professor to do the math on this one.  It’s clear that Holyrood must burn about 2.5 times as much fuel to supply Memorial’s new electricity requirements than if the University stayed with its current fuel-fired boiler.  Provincial GHG output will not be going down but will instead rise dramatically higher!

To add further injury to insult, Holyrood burns unrefined #6 fuel oil, compared to much cleaner refined #2 diesel presently used at Memorial.  This results in enormously higher production of black soot particulates and other toxins more immediately dangerous to people and the environment.

The Premier spoke at the press event of how the boiler conversion project would be the equivalent of taking over 6000 cars off the road.  If Holyrood generates the power as we should expect, the result is very much the opposite: adding 15,000 cars! 

These wouldn’t be relatively clean modern diesel cars either.  This virtual fleet of 15,000 extra cars would be noxious stinkers powered by dirty unrefined bunker fuel, with no anti-pollution equipment, driving back and forth on the roads of Conception Bay South, all day, and all night.  Think about the most choking and polluting diesel vehicles you have ever encountered and imagine these 15,000 cars all being worse. 

Transfer of Cost from MUN/GNL to Ratepayers

Another key issue conveniently ignored at the announcement event involves who would pay the excess energy cost imposed by increasing Holyrood fuel consumption.  The answer is: not Memorial.  Instead, the cost will be absorbed by all electric utility ratepayers.

The cost of the 30 million liters of extra fuel consumed at Holyrood, attributable to Memorial’s heating system electrification, will be about $35 million at current oil costs.

The extra electricity revenue coming back from Memorial likely covers just 20% of the fuel cost.  Ratepayers should expect a burden of about $28 Million to provide Memorial with their delusion of emissions reduction.  The resulting rate increase to be applied to ALL electricity customers will be 0.4 c/KWh. 

Extracting that $28 Million annually from ratepayers also negatively affects the local economy as disposable consumer capital and corporate investment capital are reduced.

The extra cost to ratepayers is not a one-time event either.  It’s annual until such time as the LIL works as intended or other new green energy sources are developed in response to the failure of the LIL.  At the snail’s pace NL Hydro and Government are moving, this is likely many years into the future.  It’s easy to see unnecessary costs to ratepayers growing to $100 Million or more.

Also, not to be forgotten is that the extra oil expenditure flows out of the province supporting indirectly if not directly all the terrible geopolitical problems that accompany oil dependency.  This new oil demand will support regimes such as Russia and Saudi Arabia whether the oil comes from there or not.

Why Does Absurdity Reign Supreme in This Province?

To recap, we are witnessing a plan that appears to be set for dismal economic and environmental failure.  

If the LIL continues to be the flop that it has been, and it appears illogical to think otherwise, then there is no reliable green energy to count upon for true fuel abatement and emissions reduction.  The more likely result is increased fuel consumption and emissions.  The emissions will also be qualitatively much more harmful.  On top of that, higher electricity rates will negatively impact the local economy and instead support foreign oil interests, supporting autocratic and despotic regimes.

To be sure, this plan is just insane and is not what any reasonable citizen of this province should want.

Of course, we know that wherever Muskrat is involved, Government should be expected to double down on their stupidity. 

Observing our University participating in this high-risk charade, however, is a new low for our province’s self-respect.  That the University has proven itself incapable of seeing the big picture here is a matter of dire concern.

Surely there must be some willing protagonists at Memorial, among students, faculty and staff, who can deliver similar analysis to challenge their executives to defer on this plan until such time as green electricity is proven to be available and reliable.  Some from Engineering and Economics are top of mind, but those in many other programs should see an opportunity to expose the high risks inherent in this undertaking.  But will they?

For the proposed project to have made it this far is frankly an outsize embarrassment for the University.  A project with far greater chance of having costly risks materialize than potential benefits should never have been approved. 

In an era of high claim to environmental awareness and climate science, the University’s commitment to such damaging risk is unforgivable and a terrible indication of subjugation to a misguided Government agenda.

That a blogsite has to provide this preliminary analysis and construct the argument against the project because the University appears incapable or unwilling to properly attend to its own business, speaks ever more poorly for the future of the institution and for the province. 

Sources and Related Reading:

Memorial University news release on boiler conversion, March 25, 2022 Emissions reduction (mun.ca)

CBC.ca report, March 26, 2022 MUN boiler to go electric with $10.5M from federal, provincial governments | CBC News

Liberty Consulting Quarterly Monitoring Report to PUB, March 11, 2022 The Liberty Consulting Group Fourteenth Quarterly Monitoring Report - 2022-03-11.PDF (pub.nl.ca)

PlanetNL28 – Electrification: Good Business or Sleight of Hand? UNCLE GNARLEY: ELECTRIFICATION: GOOD BUSINESS OR POLITICAL SLEIGHT-OF-HAND?

CBC.ca report, January 28, 2020 From fossil fuels to Muskrat: How MUN could lead the charge to electrify public buildings |CBC News